Skip to content

The Valley-Nara construction progress

The register lists The Valley-Nara in Al Yufrah 1 as complete, with a registered completion date of December 2024. Its last site inspection on record was in November 2024. The developer is Emaar Development.

100%

Built, at the site inspection of 25 November 2024

Construction complete

Registered completion date
December 2024
Construction started
December 2021
First registered
July 2021
Community
Al Yufrah 1
Units
372
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ذا فالي - نارا
Project number
2274
Site inspections
9

Schedule

The register lists The Valley-Nara as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 November 2024

100%+5.5 pts

  • The Valley-Nara construction site, inspection photo 1, 25 November 2024
  • The Valley-Nara construction site, inspection photo 2, 25 November 2024
  • The Valley-Nara construction site, inspection photo 3, 25 November 2024
  • The Valley-Nara construction site, inspection photo 4, 25 November 2024

20 August 2024

95%+21 pts

  • The Valley-Nara construction site, inspection photo 1, 20 August 2024
  • The Valley-Nara construction site, inspection photo 2, 20 August 2024
  • The Valley-Nara construction site, inspection photo 3, 20 August 2024
  • The Valley-Nara construction site, inspection photo 4, 20 August 2024

15 February 2024

74%+20 pts

  • The Valley-Nara construction site, inspection photo 1, 15 February 2024
  • The Valley-Nara construction site, inspection photo 2, 15 February 2024
  • The Valley-Nara construction site, inspection photo 3, 15 February 2024
  • The Valley-Nara construction site, inspection photo 4, 15 February 2024

20 September 2023

54%+18 pts

  • The Valley-Nara construction site, inspection photo 1, 20 September 2023
  • The Valley-Nara construction site, inspection photo 2, 20 September 2023
  • The Valley-Nara construction site, inspection photo 3, 20 September 2023
  • The Valley-Nara construction site, inspection photo 4, 20 September 2023

1 June 2023

35%+21 pts

  • The Valley-Nara construction site, inspection photo 1, 1 June 2023
  • The Valley-Nara construction site, inspection photo 2, 1 June 2023
  • The Valley-Nara construction site, inspection photo 3, 1 June 2023
  • The Valley-Nara construction site, inspection photo 4, 1 June 2023

25 January 2023

14%+11 pts

  • The Valley-Nara construction site, inspection photo 1, 25 January 2023
  • The Valley-Nara construction site, inspection photo 2, 25 January 2023
  • The Valley-Nara construction site, inspection photo 3, 25 January 2023
  • The Valley-Nara construction site, inspection photo 4, 25 January 2023

12 October 2022

3.6%+1.8 pts

  • The Valley-Nara construction site, inspection photo 1, 12 October 2022
  • The Valley-Nara construction site, inspection photo 2, 12 October 2022
  • The Valley-Nara construction site, inspection photo 3, 12 October 2022
  • The Valley-Nara construction site, inspection photo 4, 12 October 2022

1 July 2022

1.8%+0.3 pts

  • The Valley-Nara construction site, inspection photo 1, 1 July 2022
  • The Valley-Nara construction site, inspection photo 2, 1 July 2022
  • The Valley-Nara construction site, inspection photo 3, 1 July 2022

7 March 2022

1.5%

  • The Valley-Nara construction site, inspection photo 1, 7 March 2022
  • The Valley-Nara construction site, inspection photo 2, 7 March 2022
  • The Valley-Nara construction site, inspection photo 3, 7 March 2022
  • The Valley-Nara construction site, inspection photo 4, 7 March 2022

All 62 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley-Nara?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Valley-Nara handover date?
Construction of The Valley-Nara is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Valley-Nara?
The Valley-Nara was 100% built at the site inspection on 25 November 2024. The site has been inspected 9 times since March 2022. The Land Department took 62 site photos at its inspections.
Is The Valley-Nara delayed?
The register lists construction as complete.
Who is building The Valley-Nara?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley-Nara?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.