62 photos from 9 site inspections, newest first. The percentage is how much of The Valley-Nara was built on the day of each visit.

25 November 2024100% built

20 August 202495% built

15 February 202474% built

20 September 202354% built

1 June 202335% built

25 January 202314% built

12 October 20223.6% built

1 July 20221.8% built

7 March 20221.5% built

Back to The Valley-Nara construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.