Skip to content

The Valley - Elora construction progress

The register lists The Valley - Elora in Al Yufrah 1 as complete, with a registered completion date of September 2026. Its last site inspection on record was in March 2026. The developer is Emaar Development.

100%

Built, at the site inspection of 10 March 2026

Construction complete

Registered completion date
September 2026
Construction started
March 2023
First registered
January 2023
Community
Al Yufrah 1
Units
430
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا فالي - ايلورا
Project number
2511
Site inspections
10

Schedule

The register lists The Valley - Elora as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 March 2026

100%+2.1 pts

  • The Valley - Elora construction site, inspection photo 1, 10 March 2026
  • The Valley - Elora construction site, inspection photo 2, 10 March 2026
  • The Valley - Elora construction site, inspection photo 3, 10 March 2026
  • The Valley - Elora construction site, inspection photo 4, 10 March 2026

31 December 2025

98%+9.0 pts

  • The Valley - Elora construction site, inspection photo 1, 31 December 2025
  • The Valley - Elora construction site, inspection photo 2, 31 December 2025
  • The Valley - Elora construction site, inspection photo 3, 31 December 2025
  • The Valley - Elora construction site, inspection photo 4, 31 December 2025

11 September 2025

89%+5.4 pts

  • The Valley - Elora construction site, inspection photo 1, 11 September 2025
  • The Valley - Elora construction site, inspection photo 2, 11 September 2025
  • The Valley - Elora construction site, inspection photo 3, 11 September 2025
  • The Valley - Elora construction site, inspection photo 4, 11 September 2025

20 June 2025

84%+19 pts

  • The Valley - Elora construction site, inspection photo 1, 20 June 2025
  • The Valley - Elora construction site, inspection photo 2, 20 June 2025
  • The Valley - Elora construction site, inspection photo 3, 20 June 2025
  • The Valley - Elora construction site, inspection photo 4, 20 June 2025

14 February 2025

64%+23 pts

  • The Valley - Elora construction site, inspection photo 1, 14 February 2025
  • The Valley - Elora construction site, inspection photo 2, 14 February 2025
  • The Valley - Elora construction site, inspection photo 3, 14 February 2025
  • The Valley - Elora construction site, inspection photo 4, 14 February 2025

17 October 2024

42%+36 pts

  • The Valley - Elora construction site, inspection photo 1, 17 October 2024
  • The Valley - Elora construction site, inspection photo 2, 17 October 2024
  • The Valley - Elora construction site, inspection photo 3, 17 October 2024
  • The Valley - Elora construction site, inspection photo 4, 17 October 2024

22 March 2024

6.2%+4.8 pts

  • The Valley - Elora construction site, inspection photo 1, 22 March 2024
  • The Valley - Elora construction site, inspection photo 2, 22 March 2024
  • The Valley - Elora construction site, inspection photo 3, 22 March 2024
  • The Valley - Elora construction site, inspection photo 4, 22 March 2024

21 September 2023

1.3%+0.5 pts

  • The Valley - Elora construction site, inspection photo 1, 21 September 2023
  • The Valley - Elora construction site, inspection photo 2, 21 September 2023
  • The Valley - Elora construction site, inspection photo 3, 21 September 2023

1 June 2023

0.9%+0.9 pts

  • The Valley - Elora construction site, inspection photo 1, 1 June 2023
  • The Valley - Elora construction site, inspection photo 2, 1 June 2023
  • The Valley - Elora construction site, inspection photo 3, 1 June 2023

16 November 2022

0%

  • The Valley - Elora construction site, inspection photo 1, 16 November 2022
  • The Valley - Elora construction site, inspection photo 2, 16 November 2022

All 67 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Elora?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Valley - Elora handover date?
Construction of The Valley - Elora is recorded as complete, with a registered completion date of September 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Valley - Elora?
The Valley - Elora was 100% built at the site inspection on 10 March 2026. The site has been inspected 10 times since November 2022. The Land Department took 67 site photos at its inspections.
Is The Valley - Elora delayed?
The register lists construction as complete.
Who is building The Valley - Elora?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Elora?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.