67 photos from 10 site inspections, newest first. The percentage is how much of The Valley - Elora was built on the day of each visit.

10 March 2026100% built

31 December 202598% built

11 September 202589% built

20 June 202584% built

14 February 202564% built

17 October 202442% built

22 March 20246.2% built

21 September 20231.3% built

1 June 20230.9% built

16 November 20220% built

Back to The Valley - Elora construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.