The Valley - Elea construction progress
The Valley - Elea in Al Yufrah 1 is 22% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for June 2028.
22%
Built, at the Land Department site inspection of 15 July 2026
Running behind its date
- Completion date (Land Department)
- June 2028
- Finish at recent pace
- October 2029
- Construction started
- February 2025
- Registered with the Land Department
- November 2024
- Developer
- Emaar Development
- Community
- Al Yufrah 1
- Units
- 128
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا فالي - اليا
- Land Department project number
- 3406
- Land Department site inspections
- 6
Schedule
Between September 2025 and July 2026 the site added about 2.0 points a month. At that rate it would finish around October 2029, more than three months after the June 2028 date registered with the Land Department.
Site inspections
15 July 2026
22%+6.2 pts
17 March 2026
16%+7.2 pts
4 December 2025
8.6%+5.5 pts
26 September 2025
3.0%+2.1 pts
24 June 2025
0.9%+0.9 pts
15 November 2024
0%
Context
Al Yufrah 1 has 17 projects under construction, 37% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Valley - Elea?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Valley - Elea be completed?
- The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around October 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Valley - Elea is built?
- 22%, measured at the Land Department site inspection on 15 July 2026. The Land Department engineers have inspected the site 6 times since November 2024.
- Is The Valley - Elea delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building The Valley - Elea?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for The Valley - Elea?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Elwood EstatesNearby in Al Yufrah 1. 14%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)