The Valley - Elea construction progress

The registered completion date for The Valley - Elea in Al Yufrah 1 is June 2028. At the last site inspection, in July 2026, it was 22% built. The developer is Emaar Development.

22%

Built, at the site inspection of 15 July 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
October 2029
Construction started
February 2025
First registered
November 2024
Community
Al Yufrah 1
Units
128
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - اليا
Project number
3406
Site inspections
6

Schedule

Between September 2025 and July 2026 the site added about 2.0 points a month. At that rate it would finish around October 2029, more than three months after its registered date of June 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 July 2026

22%+6.2 pts

  • The Valley - Elea construction site, inspection photo 1, 15 July 2026
  • The Valley - Elea construction site, inspection photo 2, 15 July 2026
  • The Valley - Elea construction site, inspection photo 3, 15 July 2026
  • The Valley - Elea construction site, inspection photo 4, 15 July 2026

17 March 2026

16%+7.2 pts

  • The Valley - Elea construction site, inspection photo 1, 17 March 2026
  • The Valley - Elea construction site, inspection photo 2, 17 March 2026
  • The Valley - Elea construction site, inspection photo 3, 17 March 2026
  • The Valley - Elea construction site, inspection photo 4, 17 March 2026

4 December 2025

8.6%+5.5 pts

  • The Valley - Elea construction site, inspection photo 1, 4 December 2025
  • The Valley - Elea construction site, inspection photo 2, 4 December 2025
  • The Valley - Elea construction site, inspection photo 3, 4 December 2025
  • The Valley - Elea construction site, inspection photo 4, 4 December 2025

26 September 2025

3.0%+2.1 pts

  • The Valley - Elea construction site, inspection photo 1, 26 September 2025
  • The Valley - Elea construction site, inspection photo 2, 26 September 2025
  • The Valley - Elea construction site, inspection photo 3, 26 September 2025
  • The Valley - Elea construction site, inspection photo 4, 26 September 2025

24 June 2025

0.9%+0.9 pts

  • The Valley - Elea construction site, inspection photo 1, 24 June 2025
  • The Valley - Elea construction site, inspection photo 2, 24 June 2025
  • The Valley - Elea construction site, inspection photo 3, 24 June 2025
  • The Valley - Elea construction site, inspection photo 4, 24 June 2025

15 November 2024

0%

  • The Valley - Elea construction site, inspection photo 1, 15 November 2024
  • The Valley - Elea construction site, inspection photo 2, 15 November 2024

All 30 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Elea?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Elea handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Elea?
The Valley - Elea was 22% built at the site inspection on 15 July 2026. The site has been inspected 6 times since November 2024. The Land Department took 30 site photos at its inspections.
Is The Valley - Elea delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building The Valley - Elea?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Elea?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.