The Valley - Elea construction photos

30 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of The Valley - Elea was built on the day of each visit.

15 July 202622% built

17 March 202616% built

4 December 20258.6% built

26 September 20253.0% built

24 June 20250.9% built

15 November 20240% built

Back to The Valley - Elea construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.