The Valley - Avena 2 construction progress

The Valley - Avena 2 in Al Yufrah 1 is 43% built at the Land Department inspection of July 2026. Developer Emaar Development. Completion registered for July 2028.

43%

Built, at the Land Department site inspection of 20 July 2026

On pace for its date

Completion date (Land Department)
July 2028
Finish at recent pace
November 2027
Construction started
July 2024
Registered with the Land Department
July 2024
Community
Al Yufrah 1
Units
332
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - آفينا 2
Land Department project number
3159
Land Department site inspections
7

Schedule

Since September 2025 The Valley - Avena 2 has added about 3.6 points a month. That puts 100% around November 2027, within three months of its registered completion date of July 2028.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 July 2026

43%+10 pts

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 20 July 2026
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 20 July 2026
  • The Valley - Avena 2 construction site, Land Department inspection photo 3, 20 July 2026
  • The Valley - Avena 2 construction site, Land Department inspection photo 4, 20 July 2026

31 March 2026

33%+14 pts

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 31 March 2026
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 31 March 2026
  • The Valley - Avena 2 construction site, Land Department inspection photo 3, 31 March 2026
  • The Valley - Avena 2 construction site, Land Department inspection photo 4, 31 March 2026

31 December 2025

18%+11 pts

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 31 December 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 31 December 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 3, 31 December 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 4, 31 December 2025

25 September 2025

7.3%+4.4 pts

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 25 September 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 25 September 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 3, 25 September 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 4, 25 September 2025

10 June 2025

2.8%+1.1 pts

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 10 June 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 10 June 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 3, 10 June 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 4, 10 June 2025

31 January 2025

1.8%+1.8 pts

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 31 January 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 31 January 2025
  • The Valley - Avena 2 construction site, Land Department inspection photo 3, 31 January 2025

24 June 2024

0%

  • The Valley - Avena 2 construction site, Land Department inspection photo 1, 24 June 2024
  • The Valley - Avena 2 construction site, Land Department inspection photo 2, 24 June 2024

All 42 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 37% built on average. The Valley - Avena 2 is ahead of that average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Avena 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will The Valley - Avena 2 be completed?
The completion date registered with the Dubai Land Department is July 2028. At the pace of its recent inspections the site would reach 100% around November 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Valley - Avena 2 is built?
43%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 7 times since June 2024.
Is The Valley - Avena 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of July 2028.
Who is building The Valley - Avena 2?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Avena 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.