The Valley - Avena 2 construction progress

The registered completion date for The Valley - Avena 2 in Al Yufrah 1 is July 2028. At the last site inspection, in July 2026, it was 43% built. The developer is Emaar Development.

43%

Built, at the site inspection of 20 July 2026

On pace for its date

Registered completion date
July 2028
Finish at recent pace
November 2027
Construction started
July 2024
First registered
July 2024
Community
Al Yufrah 1
Units
332
Escrow bank
Emirates NBD
Name in Arabic
ذا فالي - آفينا 2
Project number
3159
Site inspections
7

Schedule

Since September 2025 The Valley - Avena 2 has added about 3.6 points a month. That puts 100% around November 2027, within three months of its registered completion date of July 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 July 2026

43%+10 pts

  • The Valley - Avena 2 construction site, inspection photo 1, 20 July 2026
  • The Valley - Avena 2 construction site, inspection photo 2, 20 July 2026
  • The Valley - Avena 2 construction site, inspection photo 3, 20 July 2026
  • The Valley - Avena 2 construction site, inspection photo 4, 20 July 2026

31 March 2026

33%+14 pts

  • The Valley - Avena 2 construction site, inspection photo 1, 31 March 2026
  • The Valley - Avena 2 construction site, inspection photo 2, 31 March 2026
  • The Valley - Avena 2 construction site, inspection photo 3, 31 March 2026
  • The Valley - Avena 2 construction site, inspection photo 4, 31 March 2026

31 December 2025

18%+11 pts

  • The Valley - Avena 2 construction site, inspection photo 1, 31 December 2025
  • The Valley - Avena 2 construction site, inspection photo 2, 31 December 2025
  • The Valley - Avena 2 construction site, inspection photo 3, 31 December 2025
  • The Valley - Avena 2 construction site, inspection photo 4, 31 December 2025

25 September 2025

7.3%+4.4 pts

  • The Valley - Avena 2 construction site, inspection photo 1, 25 September 2025
  • The Valley - Avena 2 construction site, inspection photo 2, 25 September 2025
  • The Valley - Avena 2 construction site, inspection photo 3, 25 September 2025
  • The Valley - Avena 2 construction site, inspection photo 4, 25 September 2025

10 June 2025

2.8%+1.1 pts

  • The Valley - Avena 2 construction site, inspection photo 1, 10 June 2025
  • The Valley - Avena 2 construction site, inspection photo 2, 10 June 2025
  • The Valley - Avena 2 construction site, inspection photo 3, 10 June 2025
  • The Valley - Avena 2 construction site, inspection photo 4, 10 June 2025

31 January 2025

1.8%+1.8 pts

  • The Valley - Avena 2 construction site, inspection photo 1, 31 January 2025
  • The Valley - Avena 2 construction site, inspection photo 2, 31 January 2025
  • The Valley - Avena 2 construction site, inspection photo 3, 31 January 2025

24 June 2024

0%

  • The Valley - Avena 2 construction site, inspection photo 1, 24 June 2024
  • The Valley - Avena 2 construction site, inspection photo 2, 24 June 2024

All 42 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Avena 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Avena 2 handover date?
The registered completion date is July 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Valley - Avena 2?
The Valley - Avena 2 was 43% built at the site inspection on 20 July 2026. The site has been inspected 7 times since June 2024. The Land Department took 42 site photos at its inspections.
Is The Valley - Avena 2 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of July 2028.
Who is building The Valley - Avena 2?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Avena 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.