The Valley - Avena 2 construction photos

42 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of The Valley - Avena 2 was built on the day of each visit.

20 July 202643% built

31 March 202633% built

31 December 202518% built

25 September 20257.3% built

10 June 20252.8% built

31 January 20251.8% built

24 June 20240% built

Back to The Valley - Avena 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.