The Valley - Alana construction progress

No completion date is registered for The Valley - Alana in Al Yufrah 1 yet. At the last site inspection, in July 2026, it was 82% built. The developer is Emaar Development.

82%

Built, at the site inspection of 15 July 2026

Finish at recent pace
March 2027
Construction started
November 2023
First registered
October 2023
Community
Al Yufrah 1
Units
322
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا فالي - ألانا
Project number
2803
Site inspections
9

Schedule

Since September 2025 The Valley - Alana has added about 2.2 points a month. At that rate the site reaches 100% around March 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

15 July 2026

82%+5.4 pts

  • The Valley - Alana construction site, inspection photo 1, 15 July 2026
  • The Valley - Alana construction site, inspection photo 2, 15 July 2026
  • The Valley - Alana construction site, inspection photo 3, 15 July 2026
  • The Valley - Alana construction site, inspection photo 4, 15 July 2026

24 March 2026

76%+7.0 pts

  • The Valley - Alana construction site, inspection photo 1, 24 March 2026
  • The Valley - Alana construction site, inspection photo 2, 24 March 2026
  • The Valley - Alana construction site, inspection photo 3, 24 March 2026
  • The Valley - Alana construction site, inspection photo 4, 24 March 2026

30 December 2025

69%+9.4 pts

  • The Valley - Alana construction site, inspection photo 1, 30 December 2025
  • The Valley - Alana construction site, inspection photo 2, 30 December 2025
  • The Valley - Alana construction site, inspection photo 3, 30 December 2025
  • The Valley - Alana construction site, inspection photo 4, 30 December 2025

22 September 2025

60%+11 pts

  • The Valley - Alana construction site, inspection photo 1, 22 September 2025
  • The Valley - Alana construction site, inspection photo 2, 22 September 2025
  • The Valley - Alana construction site, inspection photo 3, 22 September 2025
  • The Valley - Alana construction site, inspection photo 4, 22 September 2025

24 June 2025

48%+19 pts

  • The Valley - Alana construction site, inspection photo 1, 24 June 2025
  • The Valley - Alana construction site, inspection photo 2, 24 June 2025
  • The Valley - Alana construction site, inspection photo 3, 24 June 2025
  • The Valley - Alana construction site, inspection photo 4, 24 June 2025

10 February 2025

30%+21 pts

  • The Valley - Alana construction site, inspection photo 1, 10 February 2025
  • The Valley - Alana construction site, inspection photo 2, 10 February 2025
  • The Valley - Alana construction site, inspection photo 3, 10 February 2025
  • The Valley - Alana construction site, inspection photo 4, 10 February 2025

2 October 2024

8.9%+7.3 pts

  • The Valley - Alana construction site, inspection photo 1, 2 October 2024
  • The Valley - Alana construction site, inspection photo 2, 2 October 2024
  • The Valley - Alana construction site, inspection photo 3, 2 October 2024
  • The Valley - Alana construction site, inspection photo 4, 2 October 2024

16 May 2024

1.6%+1.6 pts

  • The Valley - Alana construction site, inspection photo 1, 16 May 2024
  • The Valley - Alana construction site, inspection photo 2, 16 May 2024
  • The Valley - Alana construction site, inspection photo 3, 16 May 2024

2 October 2023

0%

  • The Valley - Alana construction site, inspection photo 1, 2 October 2023
  • The Valley - Alana construction site, inspection photo 2, 2 October 2023

All 57 site photos, by inspection date

Context

Al Yufrah 1 has 17 projects under construction, 40% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Valley - Alana?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Valley - Alana handover date?
No completion date is on record for The Valley - Alana yet. Handover follows completion, so there is no date to give.
What is the latest construction update on The Valley - Alana?
The Valley - Alana was 82% built at the site inspection on 15 July 2026. The site has been inspected 9 times since October 2023. The Land Department took 57 site photos at its inspections.
Who is building The Valley - Alana?
The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
Which bank holds the escrow account for The Valley - Alana?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.