The Valley - Alana construction progress
The Valley - Alana in Al Yufrah 1 is 82% built at the Land Department inspection of July 2026. Developer Emaar Development.
82%
Built, at the Land Department site inspection of 15 July 2026
- Finish at recent pace
- March 2027
- Construction started
- November 2023
- Registered with the Land Department
- October 2023
- Developer
- Emaar Development
- Community
- Al Yufrah 1
- Units
- 322
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ذا فالي - ألانا
- Land Department project number
- 2803
- Land Department site inspections
- 9
Schedule
Since September 2025 The Valley - Alana has added about 2.2 points a month. At that rate the site reaches 100% around March 2027. The Land Department has no completion date on record to compare it with.
Site inspections
15 July 2026
82%+5.4 pts
24 March 2026
76%+7.0 pts
30 December 2025
69%+9.4 pts
22 September 2025
60%+11 pts
24 June 2025
48%+19 pts
10 February 2025
30%+21 pts
2 October 2024
8.9%+7.3 pts
16 May 2024
1.6%+1.6 pts
2 October 2023
0%
Context
Al Yufrah 1 has 17 projects under construction, 37% built on average.
Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Valley - Alana?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Valley - Alana be completed?
- The Land Department has no completion date on record for The Valley - Alana yet.
- How much of The Valley - Alana is built?
- 82%, measured at the Land Department site inspection on 15 July 2026. The Land Department engineers have inspected the site 9 times since October 2023.
- Who is building The Valley - Alana?
- The registered developer is Emaar Development. It has 51 other projects under construction in Dubai.
- Which bank holds the escrow account for The Valley - Alana?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The St. Regis Residences, Downtown DubaiAlso by Emaar Development. 76%, Due December 2026.
- Address The BayAlso by Emaar Development. 70%, Due December 2026.
- SeapointAlso by Emaar Development. 37%, Due March 2028.
- BayviewAlso by Emaar Development. 63%, Due July 2028.
- Elwood EstatesNearby in Al Yufrah 1. 14%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.