The Valley - Alana construction photos
57 photos from 9 site inspections, newest first. The percentage is how much of The Valley - Alana was built on the day of each visit.
15 July 202682% built
24 March 202676% built
30 December 202569% built
22 September 202560% built
24 June 202548% built
10 February 202530% built
2 October 20248.9% built
16 May 20241.6% built
2 October 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.