Zazen Gardens construction progress

The register lists Zazen Gardens in Al Furjan as complete, with a registered completion date of April 2024. Its last site inspection on record was in May 2024. The developer is Zazen Property Development.

100%

Built, at the site inspection of 24 May 2024

Construction complete

Registered completion date
April 2024
Construction started
September 2022
First registered
November 2022
Community
Al Furjan
Units
157
Escrow bank
First Abu Dhabi Bank
Name in Arabic
زازين غاردنز
Project number
2474
Site inspections
6

Schedule

The register lists Zazen Gardens as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 May 2024

100%+13 pts

  • Zazen Gardens construction site, inspection photo 1, 24 May 2024
  • Zazen Gardens construction site, inspection photo 2, 24 May 2024
  • Zazen Gardens construction site, inspection photo 3, 24 May 2024
  • Zazen Gardens construction site, inspection photo 4, 24 May 2024

15 February 2024

87%+37 pts

  • Zazen Gardens construction site, inspection photo 1, 15 February 2024
  • Zazen Gardens construction site, inspection photo 2, 15 February 2024
  • Zazen Gardens construction site, inspection photo 3, 15 February 2024
  • Zazen Gardens construction site, inspection photo 4, 15 February 2024

26 September 2023

50%+6.6 pts

  • Zazen Gardens construction site, inspection photo 1, 26 September 2023
  • Zazen Gardens construction site, inspection photo 2, 26 September 2023
  • Zazen Gardens construction site, inspection photo 3, 26 September 2023
  • Zazen Gardens construction site, inspection photo 4, 26 September 2023

8 August 2023

44%+19 pts

  • Zazen Gardens construction site, inspection photo 1, 8 August 2023
  • Zazen Gardens construction site, inspection photo 2, 8 August 2023
  • Zazen Gardens construction site, inspection photo 3, 8 August 2023
  • Zazen Gardens construction site, inspection photo 4, 8 August 2023

6 April 2023

25%+24 pts

  • Zazen Gardens construction site, inspection photo 1, 6 April 2023
  • Zazen Gardens construction site, inspection photo 2, 6 April 2023
  • Zazen Gardens construction site, inspection photo 3, 6 April 2023
  • Zazen Gardens construction site, inspection photo 4, 6 April 2023

5 October 2022

1.0%

  • Zazen Gardens construction site, inspection photo 1, 5 October 2022
  • Zazen Gardens construction site, inspection photo 2, 5 October 2022
  • Zazen Gardens construction site, inspection photo 3, 5 October 2022
  • Zazen Gardens construction site, inspection photo 4, 5 October 2022

All 47 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Zazen Property Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Zazen Gardens?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Zazen Gardens handover date?
Construction of Zazen Gardens is recorded as complete, with a registered completion date of April 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Zazen Gardens?
Zazen Gardens was 100% built at the site inspection on 24 May 2024. The site has been inspected 6 times since October 2022. The Land Department took 47 site photos at its inspections.
Is Zazen Gardens delayed?
The register lists construction as complete.
Who is building Zazen Gardens?
The registered developer is Zazen Property Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Zazen Gardens?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.