Victoria Residency construction progress

The register lists Victoria Residency in Al Furjan as complete, with a registered completion date of December 2018. Its last site inspection on record was in December 2018. The developer is C P L Real Estate Development.

100%

Built, at the site inspection of 19 December 2018

Construction complete

Registered completion date
December 2018
Construction started
August 2015
First registered
March 2016
Developer
C P L Real Estate Development
Community
Al Furjan
Units
103
Escrow bank
Mashreq Bank
Name in Arabic
فيكتوريا ريزدينس
Project number
1739
Site inspections
5

Schedule

The register lists Victoria Residency as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 December 2018

100%+18 pts

  • Victoria Residency construction site, inspection photo 1, 19 December 2018
  • Victoria Residency construction site, inspection photo 2, 19 December 2018
  • Victoria Residency construction site, inspection photo 3, 19 December 2018
  • Victoria Residency construction site, inspection photo 4, 19 December 2018

8 March 2018

82%+22 pts

  • Victoria Residency construction site, inspection photo 1, 8 March 2018
  • Victoria Residency construction site, inspection photo 2, 8 March 2018
  • Victoria Residency construction site, inspection photo 3, 8 March 2018
  • Victoria Residency construction site, inspection photo 4, 8 March 2018

31 October 2017

60%+20 pts

  • Victoria Residency construction site, inspection photo 1, 31 October 2017
  • Victoria Residency construction site, inspection photo 2, 31 October 2017
  • Victoria Residency construction site, inspection photo 3, 31 October 2017
  • Victoria Residency construction site, inspection photo 4, 31 October 2017

22 June 2017

41%+21 pts

  • Victoria Residency construction site, inspection photo 1, 22 June 2017
  • Victoria Residency construction site, inspection photo 2, 22 June 2017
  • Victoria Residency construction site, inspection photo 3, 22 June 2017
  • Victoria Residency construction site, inspection photo 4, 22 June 2017

15 January 2017

20%

  • Victoria Residency construction site, inspection photo 1, 15 January 2017
  • Victoria Residency construction site, inspection photo 2, 15 January 2017
  • Victoria Residency construction site, inspection photo 3, 15 January 2017
  • Victoria Residency construction site, inspection photo 4, 15 January 2017

All 54 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Victoria Residency?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Victoria Residency handover date?
Construction of Victoria Residency is recorded as complete, with a registered completion date of December 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Victoria Residency?
Victoria Residency was 100% built at the site inspection on 19 December 2018. The site has been inspected 5 times since January 2017. The Land Department took 54 site photos at its inspections.
Is Victoria Residency delayed?
The register lists construction as complete.
Who is building Victoria Residency?
The registered developer is C P L Real Estate Development.
Which bank holds the escrow account for Victoria Residency?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.