Valores Residences construction progress

Valores Residences in Al Furjan is 98% built at the Land Department inspection of August 2026. Developer Valores Property Development. Completion registered for August 2026.

98%

Built, at the Land Department site inspection of 31 August 2026

1 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
September 2026
Construction started
August 2024
Registered with the Land Department
September 2024
Developer
Valores Property Development
Community
Al Furjan
Units
90
Escrow bank
Mashreq Bank
Name in Arabic
فالوريس رسيدانس
Land Department project number
3068
Land Department site inspections
6

Schedule

Valores Residences was registered to complete in August 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 5.2 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 August 2026

98%+28 pts

  • Valores Residences construction site, Land Department inspection photo 1, 31 August 2026
  • Valores Residences construction site, Land Department inspection photo 2, 31 August 2026
  • Valores Residences construction site, Land Department inspection photo 3, 31 August 2026
  • Valores Residences construction site, Land Department inspection photo 4, 31 August 2026

6 April 2026

71%+10 pts

  • Valores Residences construction site, Land Department inspection photo 1, 6 April 2026
  • Valores Residences construction site, Land Department inspection photo 2, 6 April 2026
  • Valores Residences construction site, Land Department inspection photo 3, 6 April 2026
  • Valores Residences construction site, Land Department inspection photo 4, 6 April 2026

16 December 2025

60%+20 pts

  • Valores Residences construction site, Land Department inspection photo 1, 16 December 2025
  • Valores Residences construction site, Land Department inspection photo 2, 16 December 2025
  • Valores Residences construction site, Land Department inspection photo 3, 16 December 2025
  • Valores Residences construction site, Land Department inspection photo 4, 16 December 2025

25 September 2025

40%+19 pts

  • Valores Residences construction site, Land Department inspection photo 1, 25 September 2025
  • Valores Residences construction site, Land Department inspection photo 2, 25 September 2025
  • Valores Residences construction site, Land Department inspection photo 3, 25 September 2025
  • Valores Residences construction site, Land Department inspection photo 4, 25 September 2025

26 May 2025

21%+21 pts

  • Valores Residences construction site, Land Department inspection photo 1, 26 May 2025
  • Valores Residences construction site, Land Department inspection photo 2, 26 May 2025
  • Valores Residences construction site, Land Department inspection photo 3, 26 May 2025
  • Valores Residences construction site, Land Department inspection photo 4, 26 May 2025

28 May 2024

0%

  • Valores Residences construction site, Land Department inspection photo 1, 28 May 2024
  • Valores Residences construction site, Land Department inspection photo 2, 28 May 2024

All 46 site photos, by inspection date

Context

Al Furjan has 40 projects under construction, 33% built on average. Valores Residences is ahead of that average.

Valores Property Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Valores Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Valores Residences be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Valores Residences is built?
98%, measured at the Land Department site inspection on 31 August 2026. The Land Department engineers have inspected the site 6 times since May 2024.
Is Valores Residences delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Valores Residences?
The registered developer is Valores Property Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Valores Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.