Mira Villas Designed By Bentley Home construction progress
Mira Villas Designed By Bentley Home in Mohammed Bin Rashid Al Maktoum District 11 is 32% built at the Land Department inspection of July 2026. Developer M I R A Developments. Completion registered for December 2026.
32%
Built, at the Land Department site inspection of 1 July 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- October 2030
- Construction started
- August 2024
- Registered with the Land Department
- July 2024
- Developer
- M I R A Developments
- Units
- 36
- Escrow bank
- Emirates NBD
- Name in Arabic
- فلل ميرا المصممة من بنتلي هوم
- Land Department project number
- 3128
- Land Department site inspections
- 6
Schedule
Between July 2025 and July 2026 the site added about 1.3 points a month. At that rate it would finish around October 2030, more than three months after the December 2026 date registered with the Land Department.
Site inspections
1 July 2026
32%+7.2 pts
25 March 2026
25%+2.8 pts
17 December 2025
22%+4.9 pts
24 July 2025
17%+4.9 pts
27 February 2025
12%+12 pts
3 June 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.
M I R A Developments has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Mira Villas Designed By Bentley Home?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mira Villas Designed By Bentley Home be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around October 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mira Villas Designed By Bentley Home is built?
- 32%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 6 times since June 2024.
- Is Mira Villas Designed By Bentley Home delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Mira Villas Designed By Bentley Home?
- The registered developer is M I R A Developments. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Mira Villas Designed By Bentley Home?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Trussardi ResidencesAlso by M I R A Developments. 36%.
- Trussardi Residences 2Also by M I R A Developments. 4.6%.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 32%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 9.8%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 35%, Due August 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)