Flow Residences construction progress

The registered completion date for Flow Residences in Palm Deira is October 2027. At the last site inspection, in November 2026, it was 7.8% built. The developer is Main Realty Real Estate.

7.8%

Built, at the site inspection of 2 November 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
April 2036
Construction started
October 2025
First registered
June 2025
Developer
Main Realty Real Estate
Community
Palm Deira
Units
50
Escrow bank
United Bank Limited
Name in Arabic
فلو ريزيدنسز
Project number
3830
Site inspections
4

Schedule

Between February 2026 and November 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 November 2026

7.8%+3.7 pts

  • Flow Residences construction site, inspection photo 1, 2 November 2026
  • Flow Residences construction site, inspection photo 2, 2 November 2026
  • Flow Residences construction site, inspection photo 3, 2 November 2026
  • Flow Residences construction site, inspection photo 4, 2 November 2026

14 July 2026

4.1%+3.1 pts

  • Flow Residences construction site, inspection photo 1, 14 July 2026
  • Flow Residences construction site, inspection photo 2, 14 July 2026
  • Flow Residences construction site, inspection photo 3, 14 July 2026
  • Flow Residences construction site, inspection photo 4, 14 July 2026

20 February 2026

1.0%+1.0 pts

  • Flow Residences construction site, inspection photo 1, 20 February 2026
  • Flow Residences construction site, inspection photo 2, 20 February 2026
  • Flow Residences construction site, inspection photo 3, 20 February 2026
  • Flow Residences construction site, inspection photo 4, 20 February 2026

11 June 2025

0%

  • Flow Residences construction site, inspection photo 1, 11 June 2025
  • Flow Residences construction site, inspection photo 2, 11 June 2025

All 19 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Main Realty Real Estate has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Flow Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Flow Residences handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Flow Residences?
Flow Residences was 7.8% built at the site inspection on 2 November 2026. The site has been inspected 4 times since June 2025. The Land Department took 19 site photos at its inspections.
Is Flow Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Flow Residences?
The registered developer is Main Realty Real Estate. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Flow Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.