Minati Homes 1 construction photos

41 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Minati Homes 1 was built on the day of each visit.

6 July 202651% built

19 March 202643% built

17 December 202538% built

24 September 202529% built

11 June 202520% built

26 February 20259.6% built

29 November 20243.0% built

9 May 20240% built

Back to Minati Homes 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.