La Vue Parc construction progress

The registered completion date for La Vue Parc in Nad Al Sheba Gardens is September 2027. At the last site inspection, in July 2026, it was 15% built. The developer is Maaia Prime Real Estate Developers.

15%

Built, at the site inspection of 1 July 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
February 2029
Construction started
September 2025
First registered
August 2025
Developer
Maaia Prime Real Estate Developers
Units
46
Escrow bank
Emirates Islamic Bank
Name in Arabic
لا فيو بارك
Project number
3715
Site inspections
3

Schedule

Between March 2026 and July 2026 the site added about 2.6 points a month. At that rate it would finish around February 2029, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 July 2026

15%+8.4 pts

  • La Vue Parc construction site, inspection photo 1, 1 July 2026
  • La Vue Parc construction site, inspection photo 2, 1 July 2026
  • La Vue Parc construction site, inspection photo 3, 1 July 2026
  • La Vue Parc construction site, inspection photo 4, 1 July 2026

27 March 2026

7.0%+7.0 pts

  • La Vue Parc construction site, inspection photo 1, 27 March 2026
  • La Vue Parc construction site, inspection photo 2, 27 March 2026
  • La Vue Parc construction site, inspection photo 3, 27 March 2026

16 June 2025

0%

  • La Vue Parc construction site, inspection photo 1, 16 June 2025
  • La Vue Parc construction site, inspection photo 2, 16 June 2025

All 10 site photos, by inspection date

Context

Nad Al Sheba Gardens has 8 projects under construction, 52% built on average.

Maaia Prime Real Estate Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Vue Parc?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the La Vue Parc handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on La Vue Parc?
La Vue Parc was 15% built at the site inspection on 1 July 2026. The site has been inspected 3 times since June 2025. The Land Department took 10 site photos at its inspections.
Is La Vue Parc delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building La Vue Parc?
The registered developer is Maaia Prime Real Estate Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for La Vue Parc?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.