Elle Residences construction progress

The registered completion date for Elle Residences in Palm Deira is September 2027. At the last site inspection, in May 2026, it was 0% built. The developer is Anax Developments.

0%

Built, at the site inspection of 7 May 2026

Running behind its date

Registered completion date
September 2027
Construction started
November 2025
First registered
September 2025
Community
Palm Deira
Units
98
Escrow bank
United Bank Limited
Name in Arabic
إيلي ريزيدنسز
Project number
4065
Site inspections
2

Schedule

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 May 2026

0%

  • Elle Residences construction site, inspection photo 1, 7 May 2026
  • Elle Residences construction site, inspection photo 2, 7 May 2026
  • Elle Residences construction site, inspection photo 3, 7 May 2026
  • Elle Residences construction site, inspection photo 4, 7 May 2026

4 September 2025

0%

  • Elle Residences construction site, inspection photo 1, 4 September 2025
  • Elle Residences construction site, inspection photo 2, 4 September 2025

All 6 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Anax Developments has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Elle Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elle Residences handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elle Residences?
Elle Residences was 0% built at the site inspection on 7 May 2026. The site has been inspected 2 times since September 2025. The Land Department took 6 site photos at its inspections.
Is Elle Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Elle Residences?
The registered developer is Anax Developments. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Elle Residences?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.