Equiti Home construction progress

The register lists Equiti Home in Al Furjan as complete. Its last site inspection on record was in January 2026. The developer is B N H Real Estate Developer.

100%

Built, at the site inspection of 5 January 2026

Construction complete

Construction started
January 2023
First registered
February 2024
Developer
B N H Real Estate Developer
Community
Al Furjan
Units
302
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ايكويتي هوم
Project number
2863
Site inspections
8

Schedule

The register lists Equiti Home as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

5 January 2026

100%+1.5 pts

  • Equiti Home construction site, inspection photo 1, 5 January 2026
  • Equiti Home construction site, inspection photo 2, 5 January 2026
  • Equiti Home construction site, inspection photo 3, 5 January 2026
  • Equiti Home construction site, inspection photo 4, 5 January 2026

9 December 2025

99%+1.5 pts

  • Equiti Home construction site, inspection photo 1, 9 December 2025
  • Equiti Home construction site, inspection photo 2, 9 December 2025
  • Equiti Home construction site, inspection photo 3, 9 December 2025
  • Equiti Home construction site, inspection photo 4, 9 December 2025

6 November 2025

97%+2.5 pts

  • Equiti Home construction site, inspection photo 1, 6 November 2025
  • Equiti Home construction site, inspection photo 2, 6 November 2025
  • Equiti Home construction site, inspection photo 3, 6 November 2025
  • Equiti Home construction site, inspection photo 4, 6 November 2025

7 July 2025

95%+8.3 pts

  • Equiti Home construction site, inspection photo 1, 7 July 2025
  • Equiti Home construction site, inspection photo 2, 7 July 2025
  • Equiti Home construction site, inspection photo 3, 7 July 2025
  • Equiti Home construction site, inspection photo 4, 7 July 2025

19 March 2025

86%+19 pts

  • Equiti Home construction site, inspection photo 1, 19 March 2025
  • Equiti Home construction site, inspection photo 2, 19 March 2025
  • Equiti Home construction site, inspection photo 3, 19 March 2025
  • Equiti Home construction site, inspection photo 4, 19 March 2025

19 November 2024

67%+17 pts

  • Equiti Home construction site, inspection photo 1, 19 November 2024
  • Equiti Home construction site, inspection photo 2, 19 November 2024
  • Equiti Home construction site, inspection photo 3, 19 November 2024
  • Equiti Home construction site, inspection photo 4, 19 November 2024

26 July 2024

50%+15 pts

  • Equiti Home construction site, inspection photo 1, 26 July 2024
  • Equiti Home construction site, inspection photo 2, 26 July 2024
  • Equiti Home construction site, inspection photo 3, 26 July 2024
  • Equiti Home construction site, inspection photo 4, 26 July 2024

6 December 2023

35%

  • Equiti Home construction site, inspection photo 1, 6 December 2023
  • Equiti Home construction site, inspection photo 2, 6 December 2023
  • Equiti Home construction site, inspection photo 3, 6 December 2023
  • Equiti Home construction site, inspection photo 4, 6 December 2023

All 68 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

B N H Real Estate Developer has 1 project under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Equiti Home?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Equiti Home handover date?
Construction of Equiti Home is recorded as complete. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Equiti Home?
Equiti Home was 100% built at the site inspection on 5 January 2026. The site has been inspected 8 times since December 2023. The Land Department took 68 site photos at its inspections.
Is Equiti Home delayed?
The register lists construction as complete.
Who is building Equiti Home?
The registered developer is B N H Real Estate Developer. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Equiti Home?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.