Al Jawhara Tower construction progress

The register lists Al Jawhara Tower in Al Barsha South Fifth as complete, with a registered completion date of March 2020. Its last site inspection on record was in March 2020. The developer is Tiger Properties.

100%

Built, at the site inspection of 12 March 2020

Construction complete

Registered completion date
March 2020
Construction started
August 2016
First registered
September 2016
Community
Al Barsha South Fifth
Units
532
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج الجوهرة
Project number
1782
Site inspections
8

Schedule

The register lists Al Jawhara Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 March 2020

100%+5.0 pts

  • Al Jawhara Tower construction site, inspection photo 1, 12 March 2020
  • Al Jawhara Tower construction site, inspection photo 2, 12 March 2020
  • Al Jawhara Tower construction site, inspection photo 3, 12 March 2020
  • Al Jawhara Tower construction site, inspection photo 4, 12 March 2020

19 January 2020

95%+20 pts

  • Al Jawhara Tower construction site, inspection photo 1, 19 January 2020
  • Al Jawhara Tower construction site, inspection photo 2, 19 January 2020
  • Al Jawhara Tower construction site, inspection photo 3, 19 January 2020
  • Al Jawhara Tower construction site, inspection photo 4, 19 January 2020

6 August 2019

75%+24 pts

  • Al Jawhara Tower construction site, inspection photo 1, 6 August 2019
  • Al Jawhara Tower construction site, inspection photo 2, 6 August 2019
  • Al Jawhara Tower construction site, inspection photo 3, 6 August 2019
  • Al Jawhara Tower construction site, inspection photo 4, 6 August 2019

13 March 2019

51%+16 pts

  • Al Jawhara Tower construction site, inspection photo 1, 13 March 2019
  • Al Jawhara Tower construction site, inspection photo 2, 13 March 2019
  • Al Jawhara Tower construction site, inspection photo 3, 13 March 2019
  • Al Jawhara Tower construction site, inspection photo 4, 13 March 2019

3 October 2018

35%+9.5 pts

  • Al Jawhara Tower construction site, inspection photo 1, 3 October 2018
  • Al Jawhara Tower construction site, inspection photo 2, 3 October 2018
  • Al Jawhara Tower construction site, inspection photo 3, 3 October 2018
  • Al Jawhara Tower construction site, inspection photo 4, 3 October 2018

20 May 2018

25%+7.8 pts

  • Al Jawhara Tower construction site, inspection photo 1, 20 May 2018
  • Al Jawhara Tower construction site, inspection photo 2, 20 May 2018
  • Al Jawhara Tower construction site, inspection photo 3, 20 May 2018
  • Al Jawhara Tower construction site, inspection photo 4, 20 May 2018

18 February 2018

17%+11 pts

  • Al Jawhara Tower construction site, inspection photo 1, 18 February 2018
  • Al Jawhara Tower construction site, inspection photo 2, 18 February 2018
  • Al Jawhara Tower construction site, inspection photo 3, 18 February 2018
  • Al Jawhara Tower construction site, inspection photo 4, 18 February 2018

25 September 2017

6.1%

  • Al Jawhara Tower construction site, inspection photo 1, 25 September 2017
  • Al Jawhara Tower construction site, inspection photo 2, 25 September 2017
  • Al Jawhara Tower construction site, inspection photo 3, 25 September 2017
  • Al Jawhara Tower construction site, inspection photo 4, 25 September 2017

All 85 site photos, by inspection date

Context

Al Barsha South Fifth has 2 projects under construction, 42% built on average.

Tiger Properties has 8 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Al Jawhara Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Al Jawhara Tower handover date?
Construction of Al Jawhara Tower is recorded as complete, with a registered completion date of March 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Al Jawhara Tower?
Al Jawhara Tower was 100% built at the site inspection on 12 March 2020. The site has been inspected 8 times since September 2017. The Land Department took 85 site photos at its inspections.
Is Al Jawhara Tower delayed?
The register lists construction as complete.
Who is building Al Jawhara Tower?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Al Jawhara Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.