Hillside Residences 3 construction progress

Hillside Residences 3 in Wasl Gate is 13% built at the Land Department inspection of October 2026. Developer Jag Development.

13%

Built, at the Land Department site inspection of 5 October 2026

Finish at recent pace
May 2034
Construction started
January 2024
Registered with the Land Department
November 2023
Community
Wasl Gate
Units
306
Escrow bank
Emirates NBD
Name in Arabic
هيلسايد ريزيدنسيز 3
Land Department project number
2810
Land Department site inspections
6

Schedule

Since November 2025 Hillside Residences 3 has added about 1.0 points a month. At that rate the site reaches 100% around May 2034. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

5 October 2026

13%+7.4 pts

  • Hillside Residences 3 construction site, Land Department inspection photo 1, 5 October 2026
  • Hillside Residences 3 construction site, Land Department inspection photo 2, 5 October 2026
  • Hillside Residences 3 construction site, Land Department inspection photo 3, 5 October 2026
  • Hillside Residences 3 construction site, Land Department inspection photo 4, 5 October 2026

4 May 2026

5.5%+2.9 pts

  • Hillside Residences 3 construction site, Land Department inspection photo 1, 4 May 2026
  • Hillside Residences 3 construction site, Land Department inspection photo 2, 4 May 2026
  • Hillside Residences 3 construction site, Land Department inspection photo 3, 4 May 2026
  • Hillside Residences 3 construction site, Land Department inspection photo 4, 4 May 2026

14 November 2025

2.6%+0.1 pts

  • Hillside Residences 3 construction site, Land Department inspection photo 1, 14 November 2025
  • Hillside Residences 3 construction site, Land Department inspection photo 2, 14 November 2025
  • Hillside Residences 3 construction site, Land Department inspection photo 3, 14 November 2025
  • Hillside Residences 3 construction site, Land Department inspection photo 4, 14 November 2025

2 April 2025

2.6%+2.6 pts

  • Hillside Residences 3 construction site, Land Department inspection photo 1, 2 April 2025
  • Hillside Residences 3 construction site, Land Department inspection photo 2, 2 April 2025
  • Hillside Residences 3 construction site, Land Department inspection photo 3, 2 April 2025

29 May 2024

0%

  • Hillside Residences 3 construction site, Land Department inspection photo 1, 29 May 2024
  • Hillside Residences 3 construction site, Land Department inspection photo 2, 29 May 2024

11 October 2023

0%

  • Hillside Residences 3 construction site, Land Department inspection photo 1, 11 October 2023
  • Hillside Residences 3 construction site, Land Department inspection photo 2, 11 October 2023

All 22 site photos, by inspection date

Context

Wasl Gate has 13 projects under construction, 19% built on average.

Jag Development has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Hillside Residences 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Hillside Residences 3 be completed?
The Land Department has no completion date on record for Hillside Residences 3 yet.
How much of Hillside Residences 3 is built?
13%, measured at the Land Department site inspection on 5 October 2026. The Land Department engineers have inspected the site 6 times since October 2023.
Who is building Hillside Residences 3?
The registered developer is Jag Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Hillside Residences 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.