Skip to content

Hills View At Wasl Gate construction progress

The registered completion date for Hills View At Wasl Gate in Wasl Gate is June 2028. At the last site inspection, in September 2026, it was 9.1% built. The developer is Suncrest Hills Property.

9.1%

Built, at the site inspection of 24 September 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
April 2032
Construction started
June 2025
First registered
May 2025
Developer
Suncrest Hills Property
Community
Wasl Gate
Units
350
Escrow bank
The National Bank of Fujairah
Name in Arabic
هيلز فيو - وصل جيت
Project number
3627
Site inspections
3

Schedule

Between June 2026 and September 2026 the site added about 1.4 points a month. At that rate it would finish around April 2032, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 September 2026

9.1%+5.2 pts

  • Hills View At Wasl Gate construction site, inspection photo 1, 24 September 2026
  • Hills View At Wasl Gate construction site, inspection photo 2, 24 September 2026
  • Hills View At Wasl Gate construction site, inspection photo 3, 24 September 2026
  • Hills View At Wasl Gate construction site, inspection photo 4, 24 September 2026

1 June 2026

3.9%+3.9 pts

  • Hills View At Wasl Gate construction site, inspection photo 1, 1 June 2026
  • Hills View At Wasl Gate construction site, inspection photo 2, 1 June 2026
  • Hills View At Wasl Gate construction site, inspection photo 3, 1 June 2026
  • Hills View At Wasl Gate construction site, inspection photo 4, 1 June 2026

27 March 2025

0%

  • Hills View At Wasl Gate construction site, inspection photo 1, 27 March 2025
  • Hills View At Wasl Gate construction site, inspection photo 2, 27 March 2025

All 13 site photos, by inspection date

Context

Wasl Gate has 13 projects under construction, 21% built on average.

Own a unit in Hills View At Wasl Gate?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Hills View At Wasl Gate handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Hills View At Wasl Gate?
Hills View At Wasl Gate was 9.1% built at the site inspection on 24 September 2026. The site has been inspected 3 times since March 2025. The Land Department took 13 site photos at its inspections.
Is Hills View At Wasl Gate delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Hills View At Wasl Gate?
The registered developer is Suncrest Hills Property.
Which bank holds the escrow account for Hills View At Wasl Gate?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.