Hammock Park construction progress

No completion date is registered for Hammock Park in Wasl Gate yet. At the last site inspection, in September 2026, it was 82% built. The developer is Divine Hills One Real Estate Development.

82%

Built, at the site inspection of 9 September 2026

Finish at recent pace
January 2027
Construction started
February 2024
First registered
February 2024
Developer
Divine Hills One Real Estate Development
Community
Wasl Gate
Units
252
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
حاموك بارك
Project number
2920
Site inspections
7

Schedule

Since November 2025 Hammock Park has added about 4.1 points a month. At that rate the site reaches 100% around January 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

9 September 2026

82%+6.6 pts

  • Hammock Park construction site, inspection photo 1, 9 September 2026
  • Hammock Park construction site, inspection photo 2, 9 September 2026
  • Hammock Park construction site, inspection photo 3, 9 September 2026
  • Hammock Park construction site, inspection photo 4, 9 September 2026

21 May 2026

76%+24 pts

  • Hammock Park construction site, inspection photo 1, 21 May 2026
  • Hammock Park construction site, inspection photo 2, 21 May 2026
  • Hammock Park construction site, inspection photo 3, 21 May 2026
  • Hammock Park construction site, inspection photo 4, 21 May 2026

10 March 2026

51%+11 pts

  • Hammock Park construction site, inspection photo 1, 10 March 2026
  • Hammock Park construction site, inspection photo 2, 10 March 2026
  • Hammock Park construction site, inspection photo 3, 10 March 2026
  • Hammock Park construction site, inspection photo 4, 10 March 2026

7 November 2025

41%+19 pts

  • Hammock Park construction site, inspection photo 1, 7 November 2025
  • Hammock Park construction site, inspection photo 2, 7 November 2025
  • Hammock Park construction site, inspection photo 3, 7 November 2025
  • Hammock Park construction site, inspection photo 4, 7 November 2025

15 July 2025

22%+10 pts

  • Hammock Park construction site, inspection photo 1, 15 July 2025
  • Hammock Park construction site, inspection photo 2, 15 July 2025
  • Hammock Park construction site, inspection photo 3, 15 July 2025
  • Hammock Park construction site, inspection photo 4, 15 July 2025

25 March 2025

12%+12 pts

  • Hammock Park construction site, inspection photo 1, 25 March 2025
  • Hammock Park construction site, inspection photo 2, 25 March 2025
  • Hammock Park construction site, inspection photo 3, 25 March 2025
  • Hammock Park construction site, inspection photo 4, 25 March 2025

8 January 2024

0%

  • Hammock Park construction site, inspection photo 1, 8 January 2024
  • Hammock Park construction site, inspection photo 2, 8 January 2024
  • Hammock Park construction site, inspection photo 3, 8 January 2024

All 48 site photos, by inspection date

Context

Wasl Gate has 13 projects under construction, 21% built on average.

Own a unit in Hammock Park?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Hammock Park handover date?
No completion date is on record for Hammock Park yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Hammock Park?
Hammock Park was 82% built at the site inspection on 9 September 2026. The site has been inspected 7 times since January 2024. The Land Department took 48 site photos at its inspections.
Who is building Hammock Park?
The registered developer is Divine Hills One Real Estate Development.
Which bank holds the escrow account for Hammock Park?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.