Villanova Amaranta A construction progress

The register lists Villanova Amaranta A in Wadi Al Safa 5 as complete, with a registered completion date of April 2020. Its last site inspection on record was in September 2020. The developer is North Dubailand Projects.

100%

Built, at the site inspection of 24 September 2020

Construction complete

Registered completion date
April 2020
Construction started
August 2018
First registered
July 2018
Units
154
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فيلانوفا أمارانتا أ
Project number
2076
Site inspections
7

Schedule

The register lists Villanova Amaranta A as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 September 2020

100%+4.8 pts

  • Villanova Amaranta A construction site, inspection photo 1, 24 September 2020
  • Villanova Amaranta A construction site, inspection photo 2, 24 September 2020
  • Villanova Amaranta A construction site, inspection photo 3, 24 September 2020
  • Villanova Amaranta A construction site, inspection photo 4, 24 September 2020

7 July 2020

95%+2.1 pts

  • Villanova Amaranta A construction site, inspection photo 1, 7 July 2020
  • Villanova Amaranta A construction site, inspection photo 2, 7 July 2020
  • Villanova Amaranta A construction site, inspection photo 3, 7 July 2020
  • Villanova Amaranta A construction site, inspection photo 4, 7 July 2020

25 February 2020

93%+13 pts

  • Villanova Amaranta A construction site, inspection photo 1, 25 February 2020
  • Villanova Amaranta A construction site, inspection photo 2, 25 February 2020
  • Villanova Amaranta A construction site, inspection photo 3, 25 February 2020
  • Villanova Amaranta A construction site, inspection photo 4, 25 February 2020

12 November 2019

80%+36 pts

  • Villanova Amaranta A construction site, inspection photo 1, 12 November 2019
  • Villanova Amaranta A construction site, inspection photo 2, 12 November 2019
  • Villanova Amaranta A construction site, inspection photo 3, 12 November 2019
  • Villanova Amaranta A construction site, inspection photo 4, 12 November 2019

8 July 2019

44%+23 pts

  • Villanova Amaranta A construction site, inspection photo 1, 8 July 2019
  • Villanova Amaranta A construction site, inspection photo 2, 8 July 2019
  • Villanova Amaranta A construction site, inspection photo 3, 8 July 2019
  • Villanova Amaranta A construction site, inspection photo 4, 8 July 2019

26 March 2019

21%+18 pts

  • Villanova Amaranta A construction site, inspection photo 1, 26 March 2019
  • Villanova Amaranta A construction site, inspection photo 2, 26 March 2019
  • Villanova Amaranta A construction site, inspection photo 3, 26 March 2019
  • Villanova Amaranta A construction site, inspection photo 4, 26 March 2019

29 October 2018

2.6%

  • Villanova Amaranta A construction site, inspection photo 1, 29 October 2018
  • Villanova Amaranta A construction site, inspection photo 2, 29 October 2018
  • Villanova Amaranta A construction site, inspection photo 3, 29 October 2018
  • Villanova Amaranta A construction site, inspection photo 4, 29 October 2018

All 64 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Villanova Amaranta A?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Villanova Amaranta A handover date?
Construction of Villanova Amaranta A is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Villanova Amaranta A?
Villanova Amaranta A was 100% built at the site inspection on 24 September 2020. The site has been inspected 7 times since October 2018. The Land Department took 64 site photos at its inspections.
Is Villanova Amaranta A delayed?
The register lists construction as complete.
Who is building Villanova Amaranta A?
The registered developer is North Dubailand Projects. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Villanova Amaranta A?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.