Villanova Amaranta construction progress

The register lists Villanova Amaranta in Wadi Al Safa 5 as complete, with a registered completion date of May 2022. Its last site inspection on record was in May 2022. The developer is North Dubailand Projects.

100%

Built, at the site inspection of 18 May 2022

Construction complete

Registered completion date
May 2022
Construction started
January 2017
First registered
October 2016
Units
564
Escrow bank
Emirates NBD
Name in Arabic
فيلانوفا أمارنتا
Project number
1817
Site inspections
12

Schedule

The register lists Villanova Amaranta as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 May 2022

100%+1.5 pts

  • Villanova Amaranta construction site, inspection photo 1, 18 May 2022
  • Villanova Amaranta construction site, inspection photo 2, 18 May 2022
  • Villanova Amaranta construction site, inspection photo 3, 18 May 2022
  • Villanova Amaranta construction site, inspection photo 4, 18 May 2022

26 August 2021

98%+1.4 pts

  • Villanova Amaranta construction site, inspection photo 1, 26 August 2021
  • Villanova Amaranta construction site, inspection photo 2, 26 August 2021
  • Villanova Amaranta construction site, inspection photo 3, 26 August 2021
  • Villanova Amaranta construction site, inspection photo 4, 26 August 2021

8 March 2021

97%+6.0 pts

  • Villanova Amaranta construction site, inspection photo 1, 8 March 2021
  • Villanova Amaranta construction site, inspection photo 2, 8 March 2021
  • Villanova Amaranta construction site, inspection photo 3, 8 March 2021
  • Villanova Amaranta construction site, inspection photo 4, 8 March 2021

1 July 2020

91%+7.9 pts

  • Villanova Amaranta construction site, inspection photo 1, 1 July 2020
  • Villanova Amaranta construction site, inspection photo 2, 1 July 2020
  • Villanova Amaranta construction site, inspection photo 3, 1 July 2020
  • Villanova Amaranta construction site, inspection photo 4, 1 July 2020

25 February 2020

83%+8.9 pts

  • Villanova Amaranta construction site, inspection photo 1, 25 February 2020
  • Villanova Amaranta construction site, inspection photo 2, 25 February 2020
  • Villanova Amaranta construction site, inspection photo 3, 25 February 2020
  • Villanova Amaranta construction site, inspection photo 4, 25 February 2020

12 November 2019

74%+24 pts

  • Villanova Amaranta construction site, inspection photo 1, 12 November 2019
  • Villanova Amaranta construction site, inspection photo 2, 12 November 2019
  • Villanova Amaranta construction site, inspection photo 3, 12 November 2019
  • Villanova Amaranta construction site, inspection photo 4, 12 November 2019

23 June 2019

51%+23 pts

  • Villanova Amaranta construction site, inspection photo 1, 23 June 2019
  • Villanova Amaranta construction site, inspection photo 2, 23 June 2019
  • Villanova Amaranta construction site, inspection photo 3, 23 June 2019
  • Villanova Amaranta construction site, inspection photo 4, 23 June 2019

4 February 2019

28%+18 pts

  • Villanova Amaranta construction site, inspection photo 1, 4 February 2019
  • Villanova Amaranta construction site, inspection photo 2, 4 February 2019
  • Villanova Amaranta construction site, inspection photo 3, 4 February 2019
  • Villanova Amaranta construction site, inspection photo 4, 4 February 2019

10 September 2018

10%+6.4 pts

  • Villanova Amaranta construction site, inspection photo 1, 10 September 2018
  • Villanova Amaranta construction site, inspection photo 2, 10 September 2018
  • Villanova Amaranta construction site, inspection photo 3, 10 September 2018
  • Villanova Amaranta construction site, inspection photo 4, 10 September 2018

14 May 2018

3.6%+2.6 pts

  • Villanova Amaranta construction site, inspection photo 1, 14 May 2018
  • Villanova Amaranta construction site, inspection photo 2, 14 May 2018
  • Villanova Amaranta construction site, inspection photo 3, 14 May 2018
  • Villanova Amaranta construction site, inspection photo 4, 14 May 2018

All 108 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Villanova Amaranta?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Villanova Amaranta handover date?
Construction of Villanova Amaranta is recorded as complete, with a registered completion date of May 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Villanova Amaranta?
Villanova Amaranta was 100% built at the site inspection on 18 May 2022. The site has been inspected 12 times since June 2017. The Land Department took 108 site photos at its inspections.
Is Villanova Amaranta delayed?
The register lists construction as complete.
Who is building Villanova Amaranta?
The registered developer is North Dubailand Projects. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Villanova Amaranta?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.