La Tilia At Villanova Phase 1 construction photos
28 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of La Tilia At Villanova Phase 1 was built on the day of each visit.
5 October 202614% built
29 June 20265.0% built
24 March 20262.2% built
22 December 20251.3% built
8 September 20250.8% built
26 June 20250.2% built
16 December 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.