La Rosa 4 construction progress

The register lists La Rosa 4 in Wadi Al Safa 5 as complete, with a registered completion date of February 2022. Its last site inspection on record was in August 2023. The developer is North Dubailand Projects.

100%

Built, at the site inspection of 14 August 2023

Construction complete

Registered completion date
February 2022
Construction started
May 2021
First registered
March 2021
Units
178
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
4 لا روزا
Project number
2234
Site inspections
6

Schedule

The register lists La Rosa 4 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 August 2023

100%+4.2 pts

  • La Rosa 4 construction site, inspection photo 1, 14 August 2023
  • La Rosa 4 construction site, inspection photo 2, 14 August 2023
  • La Rosa 4 construction site, inspection photo 3, 14 August 2023
  • La Rosa 4 construction site, inspection photo 4, 14 August 2023

30 May 2023

96%+24 pts

  • La Rosa 4 construction site, inspection photo 1, 30 May 2023
  • La Rosa 4 construction site, inspection photo 2, 30 May 2023
  • La Rosa 4 construction site, inspection photo 3, 30 May 2023
  • La Rosa 4 construction site, inspection photo 4, 30 May 2023

8 February 2023

72%+29 pts

  • La Rosa 4 construction site, inspection photo 1, 8 February 2023
  • La Rosa 4 construction site, inspection photo 2, 8 February 2023
  • La Rosa 4 construction site, inspection photo 3, 8 February 2023
  • La Rosa 4 construction site, inspection photo 4, 8 February 2023

6 October 2022

43%+35 pts

  • La Rosa 4 construction site, inspection photo 1, 6 October 2022
  • La Rosa 4 construction site, inspection photo 2, 6 October 2022
  • La Rosa 4 construction site, inspection photo 3, 6 October 2022
  • La Rosa 4 construction site, inspection photo 4, 6 October 2022

12 May 2022

8.6%+8.3 pts

  • La Rosa 4 construction site, inspection photo 1, 12 May 2022
  • La Rosa 4 construction site, inspection photo 2, 12 May 2022
  • La Rosa 4 construction site, inspection photo 3, 12 May 2022
  • La Rosa 4 construction site, inspection photo 4, 12 May 2022

25 November 2021

0.3%

  • La Rosa 4 construction site, inspection photo 1, 25 November 2021
  • La Rosa 4 construction site, inspection photo 2, 25 November 2021
  • La Rosa 4 construction site, inspection photo 3, 25 November 2021
  • La Rosa 4 construction site, inspection photo 4, 25 November 2021

All 49 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

North Dubailand Projects has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in La Rosa 4?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the La Rosa 4 handover date?
Construction of La Rosa 4 is recorded as complete, with a registered completion date of February 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on La Rosa 4?
La Rosa 4 was 100% built at the site inspection on 14 August 2023. The site has been inspected 6 times since November 2021. The Land Department took 49 site photos at its inspections.
Is La Rosa 4 delayed?
The register lists construction as complete.
Who is building La Rosa 4?
The registered developer is North Dubailand Projects. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for La Rosa 4?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.