Athlon By Al Dar 1 construction photos
34 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Athlon By Al Dar 1 was built on the day of each visit.
23 July 202618% built
13 April 202613% built
11 December 20258.3% built
26 June 20251.5% built
10 January 20250.3% built
19 June 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.