Serra construction progress

Serra in Wadi Al Safa 4 is 42% built at the Land Department inspection of August 2026. Developer Majid Al Futtaim Ghaf Woods.

42%

Built, at the Land Department site inspection of 17 August 2026

Finish at recent pace
May 2028
Construction started
December 2024
Registered with the Land Department
May 2024
Units
535
Escrow bank
Emirates NBD
Name in Arabic
سيرا
Land Department project number
3076
Land Department site inspections
5

Schedule

Since November 2025 Serra has added about 2.8 points a month. At that rate the site reaches 100% around May 2028. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

17 August 2026

42%+3.6 pts

  • Serra construction site, Land Department inspection photo 1, 17 August 2026
  • Serra construction site, Land Department inspection photo 2, 17 August 2026
  • Serra construction site, Land Department inspection photo 3, 17 August 2026
  • Serra construction site, Land Department inspection photo 4, 17 August 2026

6 July 2026

38%+14 pts

  • Serra construction site, Land Department inspection photo 1, 6 July 2026
  • Serra construction site, Land Department inspection photo 2, 6 July 2026
  • Serra construction site, Land Department inspection photo 3, 6 July 2026
  • Serra construction site, Land Department inspection photo 4, 6 July 2026

26 March 2026

24%+6.5 pts

  • Serra construction site, Land Department inspection photo 1, 26 March 2026
  • Serra construction site, Land Department inspection photo 2, 26 March 2026
  • Serra construction site, Land Department inspection photo 3, 26 March 2026
  • Serra construction site, Land Department inspection photo 4, 26 March 2026

26 November 2025

18%+18 pts

  • Serra construction site, Land Department inspection photo 1, 26 November 2025
  • Serra construction site, Land Department inspection photo 2, 26 November 2025
  • Serra construction site, Land Department inspection photo 3, 26 November 2025
  • Serra construction site, Land Department inspection photo 4, 26 November 2025

9 May 2024

0%

  • Serra construction site, Land Department inspection photo 1, 9 May 2024

All 28 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 24% built on average.

Majid Al Futtaim Ghaf Woods has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Serra?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Serra be completed?
The Land Department has no completion date on record for Serra yet.
How much of Serra is built?
42%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 5 times since May 2024.
Who is building Serra?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Serra?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.