Serra construction progress
No completion date is registered for Serra in Wadi Al Safa 4 yet. At the last site inspection, in November 2026, it was 50% built. The developer is Majid Al Futtaim Ghaf Woods.
50%
Built, at the site inspection of 19 November 2026
- Finish at recent pace
- May 2028
- Construction started
- December 2024
- First registered
- May 2024
- Developer
- Majid Al Futtaim Ghaf Woods
- Community
- Wadi Al Safa 4
- Units
- 535
- Escrow bank
- Emirates NBD
- Name in Arabic
- سيرا
- Project number
- 3076
- Site inspections
- 6
Schedule
Since November 2025 Serra has added about 2.8 points a month. At that rate the site reaches 100% around May 2028. No completion date is on record to compare it with.
Site inspections
19 November 2026
50%+8.2 pts
17 August 2026
42%+3.6 pts
6 July 2026
38%+14 pts
26 March 2026
24%+6.5 pts
26 November 2025
18%+18 pts
9 May 2024
0%
Context
Wadi Al Safa 4 has 9 projects under construction, 27% built on average.
Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Serra?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Serra handover date?
- No completion date is on record for Serra yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Serra?
- Serra was 50% built at the site inspection on 19 November 2026. The site has been inspected 6 times since May 2024. The Land Department took 38 site photos at its inspections.
- Who is building Serra?
- The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Serra?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- CiliaAlso by Majid Al Futtaim Ghaf Woods. 44%.
- LacinaAlso by Majid Al Futtaim Ghaf Woods. 30%, Due December 2027.
- DistriktAlso by Majid Al Futtaim Ghaf Woods. 8.4%, Due September 2028.
- Capria EastAlso by Majid Al Futtaim Ghaf Woods. 7.1%, Due May 2029.
- California VillageNearby in Wadi Al Safa 4. 95%, Due July 2025, passed.
- Azizi Milan 9Nearby in Wadi Al Safa 4. 0%, Due May 2027.
- California ResidencesNearby in Wadi Al Safa 4. 1.7%, Due April 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.









.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)