Serra construction progress

No completion date is registered for Serra in Wadi Al Safa 4 yet. At the last site inspection, in November 2026, it was 50% built. The developer is Majid Al Futtaim Ghaf Woods.

50%

Built, at the site inspection of 19 November 2026

Finish at recent pace
May 2028
Construction started
December 2024
First registered
May 2024
Units
535
Escrow bank
Emirates NBD
Name in Arabic
سيرا
Project number
3076
Site inspections
6

Schedule

Since November 2025 Serra has added about 2.8 points a month. At that rate the site reaches 100% around May 2028. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

19 November 2026

50%+8.2 pts

  • Serra construction site, inspection photo 1, 19 November 2026
  • Serra construction site, inspection photo 2, 19 November 2026
  • Serra construction site, inspection photo 3, 19 November 2026
  • Serra construction site, inspection photo 4, 19 November 2026

17 August 2026

42%+3.6 pts

  • Serra construction site, inspection photo 1, 17 August 2026
  • Serra construction site, inspection photo 2, 17 August 2026
  • Serra construction site, inspection photo 3, 17 August 2026
  • Serra construction site, inspection photo 4, 17 August 2026

6 July 2026

38%+14 pts

  • Serra construction site, inspection photo 1, 6 July 2026
  • Serra construction site, inspection photo 2, 6 July 2026
  • Serra construction site, inspection photo 3, 6 July 2026
  • Serra construction site, inspection photo 4, 6 July 2026

26 March 2026

24%+6.5 pts

  • Serra construction site, inspection photo 1, 26 March 2026
  • Serra construction site, inspection photo 2, 26 March 2026
  • Serra construction site, inspection photo 3, 26 March 2026
  • Serra construction site, inspection photo 4, 26 March 2026

26 November 2025

18%+18 pts

  • Serra construction site, inspection photo 1, 26 November 2025
  • Serra construction site, inspection photo 2, 26 November 2025
  • Serra construction site, inspection photo 3, 26 November 2025
  • Serra construction site, inspection photo 4, 26 November 2025

9 May 2024

0%

  • Serra construction site, inspection photo 1, 9 May 2024

All 38 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 27% built on average.

Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Serra?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Serra handover date?
No completion date is on record for Serra yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Serra?
Serra was 50% built at the site inspection on 19 November 2026. The site has been inspected 6 times since May 2024. The Land Department took 38 site photos at its inspections.
Who is building Serra?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Serra?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.