Lacina construction progress
The registered completion date for Lacina in Wadi Al Safa 4 is December 2027. At the last site inspection, in November 2026, it was 30% built. The developer is Majid Al Futtaim Ghaf Woods.
30%
Built, at the site inspection of 3 November 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- September 2029
- Construction started
- December 2024
- First registered
- November 2024
- Developer
- Majid Al Futtaim Ghaf Woods
- Community
- Wadi Al Safa 4
- Units
- 324
- Escrow bank
- Emirates NBD
- Name in Arabic
- لاسينا
- Project number
- 3336
- Site inspections
- 5
Schedule
Between December 2025 and November 2026 the site added about 2.0 points a month. At that rate it would finish around September 2029, more than three months after its registered date of December 2027.
Site inspections
3 November 2026
30%+9.6 pts
6 July 2026
21%+8.3 pts
2 April 2026
12%+4.0 pts
8 December 2025
8.5%+8.5 pts
17 October 2024
0%
Context
Wadi Al Safa 4 has 9 projects under construction, 27% built on average.
Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Lacina?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lacina handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lacina?
- Lacina was 30% built at the site inspection on 3 November 2026. The site has been inspected 5 times since October 2024. The Land Department took 24 site photos at its inspections.
- Is Lacina delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Lacina?
- The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Lacina?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- CiliaAlso by Majid Al Futtaim Ghaf Woods. 44%.
- SerraAlso by Majid Al Futtaim Ghaf Woods. 50%.
- DistriktAlso by Majid Al Futtaim Ghaf Woods. 8.4%, Due September 2028.
- Capria EastAlso by Majid Al Futtaim Ghaf Woods. 7.1%, Due May 2029.
- California VillageNearby in Wadi Al Safa 4. 95%, Due July 2025, passed.
- Azizi Milan 9Nearby in Wadi Al Safa 4. 0%, Due May 2027.
- California ResidencesNearby in Wadi Al Safa 4. 1.7%, Due April 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.