Lacina construction progress

The registered completion date for Lacina in Wadi Al Safa 4 is December 2027. At the last site inspection, in November 2026, it was 30% built. The developer is Majid Al Futtaim Ghaf Woods.

30%

Built, at the site inspection of 3 November 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
September 2029
Construction started
December 2024
First registered
November 2024
Units
324
Escrow bank
Emirates NBD
Name in Arabic
لاسينا
Project number
3336
Site inspections
5

Schedule

Between December 2025 and November 2026 the site added about 2.0 points a month. At that rate it would finish around September 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

30%+9.6 pts

  • Lacina construction site, inspection photo 1, 3 November 2026
  • Lacina construction site, inspection photo 2, 3 November 2026
  • Lacina construction site, inspection photo 3, 3 November 2026
  • Lacina construction site, inspection photo 4, 3 November 2026

6 July 2026

21%+8.3 pts

  • Lacina construction site, inspection photo 1, 6 July 2026
  • Lacina construction site, inspection photo 2, 6 July 2026
  • Lacina construction site, inspection photo 3, 6 July 2026
  • Lacina construction site, inspection photo 4, 6 July 2026

2 April 2026

12%+4.0 pts

  • Lacina construction site, inspection photo 1, 2 April 2026
  • Lacina construction site, inspection photo 2, 2 April 2026
  • Lacina construction site, inspection photo 3, 2 April 2026
  • Lacina construction site, inspection photo 4, 2 April 2026

8 December 2025

8.5%+8.5 pts

  • Lacina construction site, inspection photo 1, 8 December 2025
  • Lacina construction site, inspection photo 2, 8 December 2025
  • Lacina construction site, inspection photo 3, 8 December 2025
  • Lacina construction site, inspection photo 4, 8 December 2025

17 October 2024

0%

  • Lacina construction site, inspection photo 1, 17 October 2024
  • Lacina construction site, inspection photo 2, 17 October 2024

All 24 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 27% built on average.

Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Lacina?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lacina handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lacina?
Lacina was 30% built at the site inspection on 3 November 2026. The site has been inspected 5 times since October 2024. The Land Department took 24 site photos at its inspections.
Is Lacina delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Lacina?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Lacina?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.