Cilia construction progress

No completion date is registered for Cilia in Wadi Al Safa 4 yet. At the last site inspection, in August 2026, it was 44% built. The developer is Majid Al Futtaim Ghaf Woods.

44%

Built, at the site inspection of 17 August 2026

Finish at recent pace
April 2028
Construction started
December 2024
First registered
June 2024
Units
546
Escrow bank
Emirates NBD
Name in Arabic
سليا
Project number
3016
Site inspections
5

Schedule

Since November 2025 Cilia has added about 2.8 points a month. At that rate the site reaches 100% around April 2028. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

17 August 2026

44%+4.3 pts

  • Cilia construction site, inspection photo 1, 17 August 2026
  • Cilia construction site, inspection photo 2, 17 August 2026
  • Cilia construction site, inspection photo 3, 17 August 2026
  • Cilia construction site, inspection photo 4, 17 August 2026

6 July 2026

40%+14 pts

  • Cilia construction site, inspection photo 1, 6 July 2026
  • Cilia construction site, inspection photo 2, 6 July 2026
  • Cilia construction site, inspection photo 3, 6 July 2026
  • Cilia construction site, inspection photo 4, 6 July 2026

26 March 2026

26%+6.4 pts

  • Cilia construction site, inspection photo 1, 26 March 2026
  • Cilia construction site, inspection photo 2, 26 March 2026
  • Cilia construction site, inspection photo 3, 26 March 2026
  • Cilia construction site, inspection photo 4, 26 March 2026

26 November 2025

20%+20 pts

  • Cilia construction site, inspection photo 1, 26 November 2025
  • Cilia construction site, inspection photo 2, 26 November 2025
  • Cilia construction site, inspection photo 3, 26 November 2025
  • Cilia construction site, inspection photo 4, 26 November 2025

9 May 2024

0%

  • Cilia construction site, inspection photo 1, 9 May 2024

All 33 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 27% built on average.

Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Cilia?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cilia handover date?
No completion date is on record for Cilia yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Cilia?
Cilia was 44% built at the site inspection on 17 August 2026. The site has been inspected 5 times since May 2024. The Land Department took 33 site photos at its inspections.
Who is building Cilia?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Cilia?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.