Distrikt construction progress

Distrikt in Wadi Al Safa 4 is 8.4% built at the Land Department inspection of August 2026. Developer Majid Al Futtaim Ghaf Woods. Completion registered for September 2028.

8.4%

Built, at the Land Department site inspection of 17 August 2026

Running behind its date

Completion date (Land Department)
September 2028
Finish at recent pace
April 2030
Construction started
August 2025
Registered with the Land Department
May 2025
Units
550
Escrow bank
Emirates NBD
Name in Arabic
ديستركت
Land Department project number
3503
Land Department site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 2.1 points a month. At that rate it would finish around April 2030, more than three months after the September 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 August 2026

8.4%+7.5 pts

  • Distrikt construction site, Land Department inspection photo 1, 17 August 2026
  • Distrikt construction site, Land Department inspection photo 2, 17 August 2026
  • Distrikt construction site, Land Department inspection photo 3, 17 August 2026
  • Distrikt construction site, Land Department inspection photo 4, 17 August 2026

30 April 2026

0.9%+0.9 pts

  • Distrikt construction site, Land Department inspection photo 1, 30 April 2026
  • Distrikt construction site, Land Department inspection photo 2, 30 April 2026
  • Distrikt construction site, Land Department inspection photo 3, 30 April 2026
  • Distrikt construction site, Land Department inspection photo 4, 30 April 2026

26 January 2025

0%

  • Distrikt construction site, Land Department inspection photo 1, 26 January 2025
  • Distrikt construction site, Land Department inspection photo 2, 26 January 2025
  • Distrikt construction site, Land Department inspection photo 3, 26 January 2025

All 14 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 24% built on average.

Majid Al Futtaim Ghaf Woods has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Distrikt?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Distrikt be completed?
The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around April 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Distrikt is built?
8.4%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 3 times since January 2025.
Is Distrikt delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Distrikt?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Distrikt?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.