Distrikt construction progress

The registered completion date for Distrikt in Wadi Al Safa 4 is September 2028. At the last site inspection, in August 2026, it was 8.4% built. The developer is Majid Al Futtaim Ghaf Woods.

8.4%

Built, at the site inspection of 17 August 2026

Running behind its date

Registered completion date
September 2028
Finish at recent pace
April 2030
Construction started
August 2025
First registered
May 2025
Units
550
Escrow bank
Emirates NBD
Name in Arabic
ديستركت
Project number
3503
Site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 2.1 points a month. At that rate it would finish around April 2030, more than three months after its registered date of September 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

8.4%+7.5 pts

  • Distrikt construction site, inspection photo 1, 17 August 2026
  • Distrikt construction site, inspection photo 2, 17 August 2026
  • Distrikt construction site, inspection photo 3, 17 August 2026
  • Distrikt construction site, inspection photo 4, 17 August 2026

30 April 2026

0.9%+0.9 pts

  • Distrikt construction site, inspection photo 1, 30 April 2026
  • Distrikt construction site, inspection photo 2, 30 April 2026
  • Distrikt construction site, inspection photo 3, 30 April 2026
  • Distrikt construction site, inspection photo 4, 30 April 2026

26 January 2025

0%

  • Distrikt construction site, inspection photo 1, 26 January 2025
  • Distrikt construction site, inspection photo 2, 26 January 2025
  • Distrikt construction site, inspection photo 3, 26 January 2025

All 14 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 27% built on average.

Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Distrikt?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Distrikt handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Distrikt?
Distrikt was 8.4% built at the site inspection on 17 August 2026. The site has been inspected 3 times since January 2025. The Land Department took 14 site photos at its inspections.
Is Distrikt delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Distrikt?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Distrikt?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.