Distrikt construction progress
Distrikt in Wadi Al Safa 4 is 8.4% built at the Land Department inspection of August 2026. Developer Majid Al Futtaim Ghaf Woods. Completion registered for September 2028.
8.4%
Built, at the Land Department site inspection of 17 August 2026
Running behind its date
- Completion date (Land Department)
- September 2028
- Finish at recent pace
- April 2030
- Construction started
- August 2025
- Registered with the Land Department
- May 2025
- Developer
- Majid Al Futtaim Ghaf Woods
- Community
- Wadi Al Safa 4
- Units
- 550
- Escrow bank
- Emirates NBD
- Name in Arabic
- ديستركت
- Land Department project number
- 3503
- Land Department site inspections
- 3
Schedule
Between April 2026 and August 2026 the site added about 2.1 points a month. At that rate it would finish around April 2030, more than three months after the September 2028 date registered with the Land Department.
Site inspections
17 August 2026
8.4%+7.5 pts
30 April 2026
0.9%+0.9 pts
26 January 2025
0%
Context
Wadi Al Safa 4 has 9 projects under construction, 24% built on average.
Majid Al Futtaim Ghaf Woods has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Distrikt?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Distrikt be completed?
- The completion date registered with the Dubai Land Department is September 2028. At the pace of its recent inspections the site would reach 100% around April 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Distrikt is built?
- 8.4%, measured at the Land Department site inspection on 17 August 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is Distrikt delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
- Who is building Distrikt?
- The registered developer is Majid Al Futtaim Ghaf Woods. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Distrikt?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- CiliaAlso by Majid Al Futtaim Ghaf Woods. 44%.
- SerraAlso by Majid Al Futtaim Ghaf Woods. 42%.
- LacinaAlso by Majid Al Futtaim Ghaf Woods. 21%, Due December 2027.
- Capria EastAlso by Majid Al Futtaim Ghaf Woods. 0.9%, Due May 2029.
- California VillageNearby in Wadi Al Safa 4. 95%, Due July 2025, passed.
- Azizi Milan 9Nearby in Wadi Al Safa 4. 0%, Due May 2027.
- California ResidencesNearby in Wadi Al Safa 4. 1.7%, Due April 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.