California Village construction progress
California Village in Wadi Al Safa 4 was registered to complete in July 2025 and is still under construction. At the last site inspection, in May 2026, it was 95% built. The developer is Gfh Real Estate.
95%
Built, at the site inspection of 8 May 2026
16 months past its registered completion date
- Registered completion date
- July 2025
- Finish at recent pace
- July 2026
- Construction started
- March 2023
- First registered
- June 2023
- Developer
- Gfh Real Estate
- Community
- Wadi Al Safa 4
- Units
- 116
- Escrow bank
- Mashreq Bank
- Name in Arabic
- كاليفورنيا فيليج
- Project number
- 2694
- Site inspections
- 8
Schedule
California Village was registered to complete in July 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
8 May 2026
95%+1.9 pts
8 December 2025
93%+14 pts
4 September 2025
79%+8.7 pts
21 May 2025
70%+19 pts
10 January 2025
52%+11 pts
12 September 2024
40%+20 pts
14 March 2024
20%+19 pts
13 June 2023
1.4%
Context
Wadi Al Safa 4 has 9 projects under construction, 27% built on average.
Gfh Real Estate has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in California Village?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the California Village handover date?
- The registered completion date was July 2025, and the register still lists California Village as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on California Village?
- California Village was 95% built at the site inspection on 8 May 2026. The site has been inspected 8 times since June 2023. The Land Department took 68 site photos at its inspections.
- Is California Village delayed?
- Yes. Its registered completion date of July 2025 has passed and the project is still listed as under construction.
- Who is building California Village?
- The registered developer is Gfh Real Estate. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for California Village?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- California ResidencesAlso by Gfh Real Estate. 1.7%, Due April 2028.
- CiliaNearby in Wadi Al Safa 4. 44%.
- SerraNearby in Wadi Al Safa 4. 50%.
- LacinaNearby in Wadi Al Safa 4. 30%, Due December 2027.
- DistriktNearby in Wadi Al Safa 4. 8.4%, Due September 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.