California Village construction progress

California Village in Wadi Al Safa 4 was registered to complete in July 2025 and is still under construction. At the last site inspection, in May 2026, it was 95% built. The developer is Gfh Real Estate.

95%

Built, at the site inspection of 8 May 2026

16 months past its registered completion date

Registered completion date
July 2025
Finish at recent pace
July 2026
Construction started
March 2023
First registered
June 2023
Developer
Gfh Real Estate
Units
116
Escrow bank
Mashreq Bank
Name in Arabic
كاليفورنيا فيليج
Project number
2694
Site inspections
8

Schedule

California Village was registered to complete in July 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around July 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 May 2026

95%+1.9 pts

  • California Village construction site, inspection photo 1, 8 May 2026
  • California Village construction site, inspection photo 2, 8 May 2026
  • California Village construction site, inspection photo 3, 8 May 2026
  • California Village construction site, inspection photo 4, 8 May 2026

8 December 2025

93%+14 pts

  • California Village construction site, inspection photo 1, 8 December 2025
  • California Village construction site, inspection photo 2, 8 December 2025
  • California Village construction site, inspection photo 3, 8 December 2025
  • California Village construction site, inspection photo 4, 8 December 2025

4 September 2025

79%+8.7 pts

  • California Village construction site, inspection photo 1, 4 September 2025
  • California Village construction site, inspection photo 2, 4 September 2025
  • California Village construction site, inspection photo 3, 4 September 2025
  • California Village construction site, inspection photo 4, 4 September 2025

21 May 2025

70%+19 pts

  • California Village construction site, inspection photo 1, 21 May 2025
  • California Village construction site, inspection photo 2, 21 May 2025
  • California Village construction site, inspection photo 3, 21 May 2025
  • California Village construction site, inspection photo 4, 21 May 2025

10 January 2025

52%+11 pts

  • California Village construction site, inspection photo 1, 10 January 2025
  • California Village construction site, inspection photo 2, 10 January 2025
  • California Village construction site, inspection photo 3, 10 January 2025
  • California Village construction site, inspection photo 4, 10 January 2025

12 September 2024

40%+20 pts

  • California Village construction site, inspection photo 1, 12 September 2024
  • California Village construction site, inspection photo 2, 12 September 2024
  • California Village construction site, inspection photo 3, 12 September 2024
  • California Village construction site, inspection photo 4, 12 September 2024

14 March 2024

20%+19 pts

  • California Village construction site, inspection photo 1, 14 March 2024
  • California Village construction site, inspection photo 2, 14 March 2024
  • California Village construction site, inspection photo 3, 14 March 2024
  • California Village construction site, inspection photo 4, 14 March 2024

13 June 2023

1.4%

  • California Village construction site, inspection photo 1, 13 June 2023
  • California Village construction site, inspection photo 2, 13 June 2023
  • California Village construction site, inspection photo 3, 13 June 2023
  • California Village construction site, inspection photo 4, 13 June 2023

All 68 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 27% built on average.

Gfh Real Estate has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in California Village?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the California Village handover date?
The registered completion date was July 2025, and the register still lists California Village as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on California Village?
California Village was 95% built at the site inspection on 8 May 2026. The site has been inspected 8 times since June 2023. The Land Department took 68 site photos at its inspections.
Is California Village delayed?
Yes. Its registered completion date of July 2025 has passed and the project is still listed as under construction.
Who is building California Village?
The registered developer is Gfh Real Estate. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for California Village?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.