California Village construction progress
California Village in Wadi Al Safa 4 is 95% built at the Land Department inspection of May 2026. Developer Gfh Real Estate. Completion registered for July 2025.
95%
Built, at the Land Department site inspection of 8 May 2026
15 months past its registered completion date
- Completion date (Land Department)
- July 2025
- Finish at recent pace
- July 2026
- Construction started
- March 2023
- Registered with the Land Department
- June 2023
- Developer
- Gfh Real Estate
- Community
- Wadi Al Safa 4
- Units
- 212
- Escrow bank
- Mashreq Bank
- Name in Arabic
- كاليفورنيا فيليج
- Land Department project number
- 2694
- Land Department site inspections
- 8
Schedule
California Village was registered to complete in July 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 2.1 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
8 May 2026
95%+1.9 pts
8 December 2025
93%+14 pts
4 September 2025
79%+8.7 pts
21 May 2025
70%+19 pts
10 January 2025
52%+11 pts
12 September 2024
40%+20 pts
14 March 2024
20%+19 pts
13 June 2023
1.4%
Context
Wadi Al Safa 4 has 9 projects under construction, 24% built on average. California Village is ahead of that average.
Gfh Real Estate has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in California Village?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will California Village be completed?
- The completion date registered with the Dubai Land Department is July 2025. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of California Village is built?
- 95%, measured at the Land Department site inspection on 8 May 2026. The Land Department engineers have inspected the site 8 times since June 2023.
- Is California Village delayed?
- Yes. Its registered completion date of July 2025 has passed and the Land Department still lists it as under construction.
- Who is building California Village?
- The registered developer is Gfh Real Estate. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for California Village?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- California ResidencesAlso by Gfh Real Estate. 1.7%, Due April 2028.
- CiliaNearby in Wadi Al Safa 4. 44%.
- SerraNearby in Wadi Al Safa 4. 42%.
- LacinaNearby in Wadi Al Safa 4. 21%, Due December 2027.
- DistriktNearby in Wadi Al Safa 4. 8.4%, Due September 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)