Capria East construction progress

Capria East in Wadi Al Safa 4 is 0.9% built at the Land Department inspection of June 2026. Developer Majid Al Futtaim Ghaf Woods. Completion registered for May 2029.

0.9%

Built, at the Land Department site inspection of 23 June 2026

Running behind its date

Completion date (Land Department)
May 2029
Finish at recent pace
June 2174
Construction started
September 2025
Registered with the Land Department
March 2025
Units
553
Escrow bank
Emirates NBD
Name in Arabic
كابريا ايست
Land Department project number
3524
Land Department site inspections
2

Schedule

Between January 2025 and June 2026 the site added about 0.1 points a month. At that rate it would finish around June 2174, more than three months after the May 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 June 2026

0.9%+0.9 pts

  • Capria East construction site, Land Department inspection photo 1, 23 June 2026
  • Capria East construction site, Land Department inspection photo 2, 23 June 2026
  • Capria East construction site, Land Department inspection photo 3, 23 June 2026

26 January 2025

0%

  • Capria East construction site, Land Department inspection photo 1, 26 January 2025
  • Capria East construction site, Land Department inspection photo 2, 26 January 2025
  • Capria East construction site, Land Department inspection photo 3, 26 January 2025

All 6 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 24% built on average.

Majid Al Futtaim Ghaf Woods has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Capria East?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Capria East be completed?
The completion date registered with the Dubai Land Department is May 2029. At the pace of its recent inspections the site would reach 100% around June 2174. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Capria East is built?
0.9%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 2 times since January 2025.
Is Capria East delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2029.
Who is building Capria East?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Capria East?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.