Capria East construction progress
The registered completion date for Capria East in Wadi Al Safa 4 is May 2029. At the last site inspection, in October 2026, it was 7.1% built. The developer is Majid Al Futtaim Ghaf Woods.
7.1%
Built, at the site inspection of 30 October 2026
Running behind its date
- Registered completion date
- May 2029
- Finish at recent pace
- February 2032
- Construction started
- September 2025
- First registered
- March 2025
- Developer
- Majid Al Futtaim Ghaf Woods
- Community
- Wadi Al Safa 4
- Units
- 553
- Escrow bank
- Emirates NBD
- Name in Arabic
- كابريا ايست
- Project number
- 3524
- Site inspections
- 3
Schedule
Between June 2026 and October 2026 the site added about 1.5 points a month. At that rate it would finish around February 2032, more than three months after its registered date of May 2029.
Site inspections
30 October 2026
7.1%+6.2 pts
23 June 2026
0.9%+0.9 pts
26 January 2025
0%
Context
Wadi Al Safa 4 has 9 projects under construction, 27% built on average.
Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Capria East?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Capria East handover date?
- The registered completion date is May 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Capria East?
- Capria East was 7.1% built at the site inspection on 30 October 2026. The site has been inspected 3 times since January 2025. The Land Department took 15 site photos at its inspections.
- Is Capria East delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2029.
- Who is building Capria East?
- The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Capria East?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- CiliaAlso by Majid Al Futtaim Ghaf Woods. 44%.
- SerraAlso by Majid Al Futtaim Ghaf Woods. 50%.
- LacinaAlso by Majid Al Futtaim Ghaf Woods. 30%, Due December 2027.
- DistriktAlso by Majid Al Futtaim Ghaf Woods. 8.4%, Due September 2028.
- California VillageNearby in Wadi Al Safa 4. 95%, Due July 2025, passed.
- Azizi Milan 9Nearby in Wadi Al Safa 4. 0%, Due May 2027.
- California ResidencesNearby in Wadi Al Safa 4. 1.7%, Due April 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)