Capria East construction progress

The registered completion date for Capria East in Wadi Al Safa 4 is May 2029. At the last site inspection, in October 2026, it was 7.1% built. The developer is Majid Al Futtaim Ghaf Woods.

7.1%

Built, at the site inspection of 30 October 2026

Running behind its date

Registered completion date
May 2029
Finish at recent pace
February 2032
Construction started
September 2025
First registered
March 2025
Units
553
Escrow bank
Emirates NBD
Name in Arabic
كابريا ايست
Project number
3524
Site inspections
3

Schedule

Between June 2026 and October 2026 the site added about 1.5 points a month. At that rate it would finish around February 2032, more than three months after its registered date of May 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 October 2026

7.1%+6.2 pts

  • Capria East construction site, inspection photo 1, 30 October 2026
  • Capria East construction site, inspection photo 2, 30 October 2026
  • Capria East construction site, inspection photo 3, 30 October 2026
  • Capria East construction site, inspection photo 4, 30 October 2026

23 June 2026

0.9%+0.9 pts

  • Capria East construction site, inspection photo 1, 23 June 2026
  • Capria East construction site, inspection photo 2, 23 June 2026
  • Capria East construction site, inspection photo 3, 23 June 2026

26 January 2025

0%

  • Capria East construction site, inspection photo 1, 26 January 2025
  • Capria East construction site, inspection photo 2, 26 January 2025
  • Capria East construction site, inspection photo 3, 26 January 2025

All 15 site photos, by inspection date

Context

Wadi Al Safa 4 has 9 projects under construction, 27% built on average.

Majid Al Futtaim Ghaf Woods has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Capria East?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Capria East handover date?
The registered completion date is May 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Capria East?
Capria East was 7.1% built at the site inspection on 30 October 2026. The site has been inspected 3 times since January 2025. The Land Department took 15 site photos at its inspections.
Is Capria East delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2029.
Who is building Capria East?
The registered developer is Majid Al Futtaim Ghaf Woods. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Capria East?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.