The Wilds 3 construction progress

The Wilds 3 in Wadi Al Safa 3 is 3.1% built at the Land Department inspection of September 2026. Developer Aurora Spv 2. Completion registered for May 2029.

3.1%

Built, at the Land Department site inspection of 14 September 2026

Running behind its date

Completion date (Land Department)
May 2029
Finish at recent pace
June 2068
Construction started
July 2025
Registered with the Land Department
May 2025
Developer
Aurora Spv 2
Units
408
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا وايلدز 3
Land Department project number
3607
Land Department site inspections
4

Schedule

Between February 2026 and September 2026 the site added about 0.2 points a month. At that rate it would finish around June 2068, more than three months after the May 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 September 2026

3.1%+0.7 pts

  • The Wilds 3 construction site, Land Department inspection photo 1, 14 September 2026
  • The Wilds 3 construction site, Land Department inspection photo 2, 14 September 2026
  • The Wilds 3 construction site, Land Department inspection photo 3, 14 September 2026
  • The Wilds 3 construction site, Land Department inspection photo 4, 14 September 2026

16 June 2026

2.4%+0.6 pts

  • The Wilds 3 construction site, Land Department inspection photo 1, 16 June 2026
  • The Wilds 3 construction site, Land Department inspection photo 2, 16 June 2026
  • The Wilds 3 construction site, Land Department inspection photo 3, 16 June 2026

20 February 2026

1.8%+1.8 pts

  • The Wilds 3 construction site, Land Department inspection photo 1, 20 February 2026
  • The Wilds 3 construction site, Land Department inspection photo 2, 20 February 2026
  • The Wilds 3 construction site, Land Department inspection photo 3, 20 February 2026
  • The Wilds 3 construction site, Land Department inspection photo 4, 20 February 2026

24 March 2025

0%

  • The Wilds 3 construction site, Land Department inspection photo 1, 24 March 2025
  • The Wilds 3 construction site, Land Department inspection photo 2, 24 March 2025

All 17 site photos, by inspection date

Context

Wadi Al Safa 3 has 3 projects under construction, 7.8% built on average.

Aurora Spv 2 has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Wilds 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Wilds 3 be completed?
The completion date registered with the Dubai Land Department is May 2029. At the pace of its recent inspections the site would reach 100% around June 2068. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Wilds 3 is built?
3.1%, measured at the Land Department site inspection on 14 September 2026. The Land Department engineers have inspected the site 4 times since March 2025.
Is The Wilds 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2029.
Who is building The Wilds 3?
The registered developer is Aurora Spv 2. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Wilds 3?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.