The Wilds 3 construction progress
The registered completion date for The Wilds 3 in Wadi Al Safa 3 is May 2029. At the last site inspection, in September 2026, it was 3.1% built. The developer is Aurora Spv 2.
3.1%
Built, at the site inspection of 14 September 2026
Running behind its date
- Registered completion date
- May 2029
- Finish at recent pace
- June 2068
- Construction started
- July 2025
- First registered
- May 2025
- Developer
- Aurora Spv 2
- Community
- Wadi Al Safa 3
- Units
- 408
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ذا وايلدز 3
- Project number
- 3607
- Site inspections
- 4
Schedule
Between February 2026 and September 2026 the site added about 0.2 points a month. At that rate it would finish around June 2068, more than three months after its registered date of May 2029.
Site inspections
14 September 2026
3.1%+0.7 pts
16 June 2026
2.4%+0.6 pts
20 February 2026
1.8%+1.8 pts
24 March 2025
0%
Context
Wadi Al Safa 3 has 3 projects under construction, 7.8% built on average.
Aurora Spv 2 has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Wilds 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Wilds 3 handover date?
- The registered completion date is May 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2068. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Wilds 3?
- The Wilds 3 was 3.1% built at the site inspection on 14 September 2026. The site has been inspected 4 times since March 2025. The Land Department took 17 site photos at its inspections.
- Is The Wilds 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2029.
- Who is building The Wilds 3?
- The registered developer is Aurora Spv 2. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for The Wilds 3?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Wilds 1Also by Aurora Spv 2. 7.5%, Due January 2029.
- The Wilds 2Also by Aurora Spv 2. 5.7%, Due February 2029.
- The Wilds ResidencesAlso by Aurora Spv 2. 0%, Due June 2030.
- Taormina Village 1Nearby in Wadi Al Safa 3. 20%, Due December 2027.
- Taormina Village 2Nearby in Wadi Al Safa 3. 0%, Due July 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


