Sobha Reserve construction progress
Sobha Reserve in Wadi Al Safa 2 is 75% built at the Land Department inspection of August 2026. Developer Sobha.
75%
Built, at the Land Department site inspection of 5 August 2026
- Finish at recent pace
- July 2027
- Construction started
- October 2023
- Registered with the Land Department
- December 2023
- Developer
- Sobha
- Community
- Wadi Al Safa 2
- Units
- 351
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- شوبا ريزرف
- Land Department project number
- 2826
- Land Department site inspections
- 9
Schedule
Since November 2025 Sobha Reserve has added about 2.2 points a month. At that rate the site reaches 100% around July 2027. The Land Department has no completion date on record to compare it with.
Site inspections
5 August 2026
75%+9.1 pts
26 March 2026
66%+11 pts
4 November 2025
55%+12 pts
16 June 2025
43%+17 pts
5 March 2025
26%+8.6 pts
24 December 2024
17%+4.0 pts
17 October 2024
13%+6.4 pts
23 May 2024
6.7%+6.0 pts
28 November 2023
0.7%
Context
Wadi Al Safa 2 has 2 projects under construction, 66% built on average. Sobha Reserve is ahead of that average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Reserve?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Sobha Reserve be completed?
- The Land Department has no completion date on record for Sobha Reserve yet. It appears once the developer registers the construction timeline.
- How much of Sobha Reserve is built?
- 75%, measured at the Land Department site inspection on 5 August 2026. The Land Department engineers have inspected the site 9 times since November 2023.
- Who is building Sobha Reserve?
- The registered developer is Sobha. It has 26 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Reserve?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 37%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vistas HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- BiancaNearby in Wadi Al Safa 2. 56%, Due December 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)