Sobha Reserve construction photos
79 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Sobha Reserve was built on the day of each visit.
5 August 202675% built
26 March 202666% built
4 November 202555% built
16 June 202543% built
5 March 202526% built
24 December 202417% built
17 October 202413% built
23 May 20246.7% built
28 November 20230.7% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.