Plagette 32 construction progress
No completion date is registered for Plagette 32 in Tilal Al Ghaf yet. At the last site inspection, in November 2026, it was 70% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.
70%
Built, at the site inspection of 17 November 2026
- Finish at recent pace
- September 2027
- Construction started
- June 2024
- First registered
- November 2023
- Community
- Tilal Al Ghaf
- Units
- 32
- Escrow bank
- Emirates NBD
- Name in Arabic
- بلاجيت 32
- Project number
- 2827
- Site inspections
- 8
Schedule
Since January 2026 Plagette 32 has added about 2.9 points a month. At that rate the site reaches 100% around September 2027. No completion date is on record to compare it with.
Site inspections
17 November 2026
70%+9.5 pts
13 August 2026
61%+7.2 pts
8 July 2026
53%+8.0 pts
30 March 2026
45%+3.3 pts
26 January 2026
42%+35 pts
8 September 2025
7.1%+5.3 pts
24 January 2025
1.8%+1.8 pts
26 October 2023
0%
Context
Tilal Al Ghaf has 6 projects under construction, 73% built on average.
Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Plagette 32?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Plagette 32 handover date?
- No completion date is on record for Plagette 32 yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Plagette 32?
- Plagette 32 was 70% built at the site inspection on 17 November 2026. The site has been inspected 8 times since October 2023. The Land Department took 52 site photos at its inspections.
- Who is building Plagette 32?
- The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Plagette 32?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elysian MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 95%, Due March 2025, passed.
- AlayaAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 94%, Due July 2026, passed.
- Lanai IslandAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 61%, Due September 2026, passed.
- Serenity MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 40%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)