Plagette 32 construction progress
Plagette 32 in Tilal Al Ghaf is 61% built at the Land Department inspection of August 2026. Developer Majid Al Futtaim Tilal Al Ghaf Phase A.
61%
Built, at the Land Department site inspection of 13 August 2026
- Finish at recent pace
- April 2027
- Construction started
- June 2024
- Registered with the Land Department
- November 2023
- Community
- Tilal Al Ghaf
- Units
- 32
- Escrow bank
- Emirates NBD
- Name in Arabic
- بلاجيت 32
- Land Department project number
- 2827
- Land Department site inspections
- 7
Schedule
Since September 2025 Plagette 32 has added about 4.8 points a month. At that rate the site reaches 100% around April 2027. The Land Department has no completion date on record to compare it with.
Site inspections
13 August 2026
61%+7.2 pts
8 July 2026
53%+8.0 pts
30 March 2026
45%+3.3 pts
26 January 2026
42%+35 pts
8 September 2025
7.1%+5.3 pts
24 January 2025
1.8%+1.8 pts
26 October 2023
0%
Context
Tilal Al Ghaf has 5 projects under construction, 64% built on average. Plagette 32 is behind that average.
Majid Al Futtaim Tilal Al Ghaf Phase A has 5 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Plagette 32?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Plagette 32 be completed?
- The Land Department has no completion date on record for Plagette 32 yet. It appears once the developer registers the construction timeline.
- How much of Plagette 32 is built?
- 61%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 7 times since October 2023.
- Who is building Plagette 32?
- The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Plagette 32?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elysian MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 95%, Due March 2025, passed.
- Lanai IslandAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 61%, Due September 2026, passed.
- Serenity MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 32%.
- AmaraAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 71%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.