Plagette 32 construction progress

No completion date is registered for Plagette 32 in Tilal Al Ghaf yet. At the last site inspection, in November 2026, it was 70% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

70%

Built, at the site inspection of 17 November 2026

Finish at recent pace
September 2027
Construction started
June 2024
First registered
November 2023
Community
Tilal Al Ghaf
Units
32
Escrow bank
Emirates NBD
Name in Arabic
بلاجيت 32
Project number
2827
Site inspections
8

Schedule

Since January 2026 Plagette 32 has added about 2.9 points a month. At that rate the site reaches 100% around September 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

17 November 2026

70%+9.5 pts

  • Plagette 32 construction site, inspection photo 1, 17 November 2026
  • Plagette 32 construction site, inspection photo 2, 17 November 2026
  • Plagette 32 construction site, inspection photo 3, 17 November 2026
  • Plagette 32 construction site, inspection photo 4, 17 November 2026

13 August 2026

61%+7.2 pts

  • Plagette 32 construction site, inspection photo 1, 13 August 2026
  • Plagette 32 construction site, inspection photo 2, 13 August 2026
  • Plagette 32 construction site, inspection photo 3, 13 August 2026
  • Plagette 32 construction site, inspection photo 4, 13 August 2026

8 July 2026

53%+8.0 pts

  • Plagette 32 construction site, inspection photo 1, 8 July 2026
  • Plagette 32 construction site, inspection photo 2, 8 July 2026
  • Plagette 32 construction site, inspection photo 3, 8 July 2026
  • Plagette 32 construction site, inspection photo 4, 8 July 2026

30 March 2026

45%+3.3 pts

  • Plagette 32 construction site, inspection photo 1, 30 March 2026
  • Plagette 32 construction site, inspection photo 2, 30 March 2026
  • Plagette 32 construction site, inspection photo 3, 30 March 2026
  • Plagette 32 construction site, inspection photo 4, 30 March 2026

26 January 2026

42%+35 pts

  • Plagette 32 construction site, inspection photo 1, 26 January 2026
  • Plagette 32 construction site, inspection photo 2, 26 January 2026
  • Plagette 32 construction site, inspection photo 3, 26 January 2026
  • Plagette 32 construction site, inspection photo 4, 26 January 2026

8 September 2025

7.1%+5.3 pts

  • Plagette 32 construction site, inspection photo 1, 8 September 2025
  • Plagette 32 construction site, inspection photo 2, 8 September 2025
  • Plagette 32 construction site, inspection photo 3, 8 September 2025
  • Plagette 32 construction site, inspection photo 4, 8 September 2025

24 January 2025

1.8%+1.8 pts

  • Plagette 32 construction site, inspection photo 1, 24 January 2025
  • Plagette 32 construction site, inspection photo 2, 24 January 2025
  • Plagette 32 construction site, inspection photo 3, 24 January 2025

26 October 2023

0%

  • Plagette 32 construction site, inspection photo 1, 26 October 2023
  • Plagette 32 construction site, inspection photo 2, 26 October 2023

All 52 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Plagette 32?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Plagette 32 handover date?
No completion date is on record for Plagette 32 yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Plagette 32?
Plagette 32 was 70% built at the site inspection on 17 November 2026. The site has been inspected 8 times since October 2023. The Land Department took 52 site photos at its inspections.
Who is building Plagette 32?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Plagette 32?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.