Serenity Mansions construction progress
No completion date is registered for Serenity Mansions in Tilal Al Ghaf yet. At the last site inspection, in November 2026, it was 40% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.
40%
Built, at the site inspection of 10 November 2026
- Finish at recent pace
- September 2028
- Construction started
- December 2023
- First registered
- October 2023
- Community
- Tilal Al Ghaf
- Units
- 110
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- سيرينيتي مانشنز
- Project number
- 2718
- Site inspections
- 9
Schedule
Since January 2026 Serenity Mansions has added about 2.6 points a month. At that rate the site reaches 100% around September 2028. No completion date is on record to compare it with.
Site inspections
10 November 2026
40%+7.7 pts
7 September 2026
32%+9.6 pts
13 May 2026
23%+4.6 pts
25 March 2026
18%+4.3 pts
13 January 2026
14%+7.7 pts
9 October 2025
6.2%+1.0 pts
24 September 2025
5.3%+4.7 pts
6 March 2025
0.6%+0.6 pts
25 July 2023
0%
Context
Tilal Al Ghaf has 6 projects under construction, 73% built on average.
Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Serenity Mansions?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Serenity Mansions handover date?
- No completion date is on record for Serenity Mansions yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Serenity Mansions?
- Serenity Mansions was 40% built at the site inspection on 10 November 2026. The site has been inspected 9 times since July 2023. The Land Department took 70 site photos at its inspections.
- Who is building Serenity Mansions?
- The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Serenity Mansions?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elysian MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 95%, Due March 2025, passed.
- AlayaAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 94%, Due July 2026, passed.
- Lanai IslandAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 61%, Due September 2026, passed.
- Plagette 32Also by Majid Al Futtaim Tilal Al Ghaf Phase A. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.