Serenity Mansions construction progress

No completion date is registered for Serenity Mansions in Tilal Al Ghaf yet. At the last site inspection, in November 2026, it was 40% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

40%

Built, at the site inspection of 10 November 2026

Finish at recent pace
September 2028
Construction started
December 2023
First registered
October 2023
Community
Tilal Al Ghaf
Units
110
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سيرينيتي مانشنز
Project number
2718
Site inspections
9

Schedule

Since January 2026 Serenity Mansions has added about 2.6 points a month. At that rate the site reaches 100% around September 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

10 November 2026

40%+7.7 pts

  • Serenity Mansions construction site, inspection photo 1, 10 November 2026
  • Serenity Mansions construction site, inspection photo 2, 10 November 2026
  • Serenity Mansions construction site, inspection photo 3, 10 November 2026
  • Serenity Mansions construction site, inspection photo 4, 10 November 2026

7 September 2026

32%+9.6 pts

  • Serenity Mansions construction site, inspection photo 1, 7 September 2026
  • Serenity Mansions construction site, inspection photo 2, 7 September 2026
  • Serenity Mansions construction site, inspection photo 3, 7 September 2026
  • Serenity Mansions construction site, inspection photo 4, 7 September 2026

13 May 2026

23%+4.6 pts

  • Serenity Mansions construction site, inspection photo 1, 13 May 2026
  • Serenity Mansions construction site, inspection photo 2, 13 May 2026
  • Serenity Mansions construction site, inspection photo 3, 13 May 2026
  • Serenity Mansions construction site, inspection photo 4, 13 May 2026

25 March 2026

18%+4.3 pts

  • Serenity Mansions construction site, inspection photo 1, 25 March 2026
  • Serenity Mansions construction site, inspection photo 2, 25 March 2026
  • Serenity Mansions construction site, inspection photo 3, 25 March 2026
  • Serenity Mansions construction site, inspection photo 4, 25 March 2026

13 January 2026

14%+7.7 pts

  • Serenity Mansions construction site, inspection photo 1, 13 January 2026
  • Serenity Mansions construction site, inspection photo 2, 13 January 2026
  • Serenity Mansions construction site, inspection photo 3, 13 January 2026
  • Serenity Mansions construction site, inspection photo 4, 13 January 2026

9 October 2025

6.2%+1.0 pts

  • Serenity Mansions construction site, inspection photo 1, 9 October 2025
  • Serenity Mansions construction site, inspection photo 2, 9 October 2025
  • Serenity Mansions construction site, inspection photo 3, 9 October 2025
  • Serenity Mansions construction site, inspection photo 4, 9 October 2025

24 September 2025

5.3%+4.7 pts

  • Serenity Mansions construction site, inspection photo 1, 24 September 2025
  • Serenity Mansions construction site, inspection photo 2, 24 September 2025
  • Serenity Mansions construction site, inspection photo 3, 24 September 2025
  • Serenity Mansions construction site, inspection photo 4, 24 September 2025

6 March 2025

0.6%+0.6 pts

  • Serenity Mansions construction site, inspection photo 1, 6 March 2025
  • Serenity Mansions construction site, inspection photo 2, 6 March 2025
  • Serenity Mansions construction site, inspection photo 3, 6 March 2025

25 July 2023

0%

  • Serenity Mansions construction site, inspection photo 1, 25 July 2023
  • Serenity Mansions construction site, inspection photo 2, 25 July 2023
  • Serenity Mansions construction site, inspection photo 3, 25 July 2023

All 70 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Serenity Mansions?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Serenity Mansions handover date?
No completion date is on record for Serenity Mansions yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Serenity Mansions?
Serenity Mansions was 40% built at the site inspection on 10 November 2026. The site has been inspected 9 times since July 2023. The Land Department took 70 site photos at its inspections.
Who is building Serenity Mansions?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Serenity Mansions?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.