Plagette 32 construction photos
52 photos from 8 site inspections, newest first. The percentage is how much of Plagette 32 was built on the day of each visit.
17 November 202670% built
13 August 202661% built
8 July 202653% built
30 March 202645% built
26 January 202642% built
8 September 20257.1% built
24 January 20251.8% built
26 October 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.