Elysian Mansions construction progress

Elysian Mansions in Tilal Al Ghaf is 95% built at the Land Department inspection of August 2026. Developer Majid Al Futtaim Tilal Al Ghaf Phase A. Completion registered for March 2025.

95%

Built, at the Land Department site inspection of 14 August 2026

18 months past its registered completion date

Completion date (Land Department)
March 2025
Finish at recent pace
December 2026
Construction started
September 2018
Registered with the Land Department
April 2018
Community
Tilal Al Ghaf
Units
35
Escrow bank
Emirates NBD
Name in Arabic
إليزيان مانشنس
Land Department project number
2054
Land Department site inspections
14

Schedule

Elysian Mansions was registered to complete in March 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%2019202120232025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 August 2026

95%+2.0 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 14 August 2026
  • Elysian Mansions construction site, Land Department inspection photo 2, 14 August 2026
  • Elysian Mansions construction site, Land Department inspection photo 3, 14 August 2026
  • Elysian Mansions construction site, Land Department inspection photo 4, 14 August 2026

25 June 2026

93%+0.9 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 25 June 2026
  • Elysian Mansions construction site, Land Department inspection photo 2, 25 June 2026
  • Elysian Mansions construction site, Land Department inspection photo 3, 25 June 2026
  • Elysian Mansions construction site, Land Department inspection photo 4, 25 June 2026

4 June 2026

92%+1.0 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 4 June 2026
  • Elysian Mansions construction site, Land Department inspection photo 2, 4 June 2026
  • Elysian Mansions construction site, Land Department inspection photo 3, 4 June 2026
  • Elysian Mansions construction site, Land Department inspection photo 4, 4 June 2026

21 April 2026

91%+3.1 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 21 April 2026
  • Elysian Mansions construction site, Land Department inspection photo 2, 21 April 2026
  • Elysian Mansions construction site, Land Department inspection photo 3, 21 April 2026
  • Elysian Mansions construction site, Land Department inspection photo 4, 21 April 2026

21 January 2026

88%+8.5 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 21 January 2026
  • Elysian Mansions construction site, Land Department inspection photo 2, 21 January 2026
  • Elysian Mansions construction site, Land Department inspection photo 3, 21 January 2026
  • Elysian Mansions construction site, Land Department inspection photo 4, 21 January 2026

9 September 2025

80%+14 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 9 September 2025
  • Elysian Mansions construction site, Land Department inspection photo 2, 9 September 2025
  • Elysian Mansions construction site, Land Department inspection photo 3, 9 September 2025
  • Elysian Mansions construction site, Land Department inspection photo 4, 9 September 2025

16 June 2025

66%+20 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 16 June 2025
  • Elysian Mansions construction site, Land Department inspection photo 2, 16 June 2025
  • Elysian Mansions construction site, Land Department inspection photo 3, 16 June 2025
  • Elysian Mansions construction site, Land Department inspection photo 4, 16 June 2025

27 December 2024

46%+8.6 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 27 December 2024
  • Elysian Mansions construction site, Land Department inspection photo 2, 27 December 2024
  • Elysian Mansions construction site, Land Department inspection photo 3, 27 December 2024
  • Elysian Mansions construction site, Land Department inspection photo 4, 27 December 2024

31 October 2024

37%+22 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 31 October 2024
  • Elysian Mansions construction site, Land Department inspection photo 2, 31 October 2024
  • Elysian Mansions construction site, Land Department inspection photo 3, 31 October 2024
  • Elysian Mansions construction site, Land Department inspection photo 4, 31 October 2024

16 July 2024

16%+3.7 pts

  • Elysian Mansions construction site, Land Department inspection photo 1, 16 July 2024
  • Elysian Mansions construction site, Land Department inspection photo 2, 16 July 2024
  • Elysian Mansions construction site, Land Department inspection photo 3, 16 July 2024
  • Elysian Mansions construction site, Land Department inspection photo 4, 16 July 2024

All 100 site photos, by inspection date

Context

Tilal Al Ghaf has 5 projects under construction, 64% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Elysian Mansions?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elysian Mansions be completed?
The completion date registered with the Dubai Land Department is March 2025. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Elysian Mansions is built?
95%, measured at the Land Department site inspection on 14 August 2026. The Land Department engineers have inspected the site 14 times since February 2022.
Is Elysian Mansions delayed?
Yes. Its registered completion date of March 2025 has passed and the Land Department still lists it as under construction.
Who is building Elysian Mansions?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Elysian Mansions?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.