Elysian Mansions construction progress
Elysian Mansions in Tilal Al Ghaf was registered to complete in March 2025 and is still under construction. At the last site inspection, in August 2026, it was 95% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.
95%
Built, at the site inspection of 14 August 2026
20 months past its registered completion date
- Registered completion date
- March 2025
- Finish at recent pace
- December 2026
- Construction started
- September 2018
- First registered
- April 2018
- Community
- Tilal Al Ghaf
- Units
- 35
- Escrow bank
- Emirates NBD
- Name in Arabic
- إليزيان مانشنس
- Project number
- 2054
- Site inspections
- 14
Schedule
Elysian Mansions was registered to complete in March 2025, 20 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around December 2026.
Site inspections
14 August 2026
95%+2.0 pts
25 June 2026
93%+0.9 pts
4 June 2026
92%+1.0 pts
21 April 2026
91%+3.1 pts
21 January 2026
88%+8.5 pts
9 September 2025
80%+14 pts
16 June 2025
66%+20 pts
27 December 2024
46%+8.6 pts
31 October 2024
37%+22 pts
16 July 2024
16%+3.7 pts
Context
Tilal Al Ghaf has 6 projects under construction, 73% built on average.
Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Elysian Mansions?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Elysian Mansions handover date?
- The registered completion date was March 2025, and the register still lists Elysian Mansions as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Elysian Mansions?
- Elysian Mansions was 95% built at the site inspection on 14 August 2026. The site has been inspected 14 times since February 2022. The Land Department took 100 site photos at its inspections.
- Is Elysian Mansions delayed?
- Yes. Its registered completion date of March 2025 has passed and the project is still listed as under construction.
- Who is building Elysian Mansions?
- The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Elysian Mansions?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- AlayaAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 94%, Due July 2026, passed.
- Lanai IslandAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 61%, Due September 2026, passed.
- Serenity MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 40%.
- Plagette 32Also by Majid Al Futtaim Tilal Al Ghaf Phase A. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.