Elysian Mansions construction progress

Elysian Mansions in Tilal Al Ghaf was registered to complete in March 2025 and is still under construction. At the last site inspection, in August 2026, it was 95% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

95%

Built, at the site inspection of 14 August 2026

20 months past its registered completion date

Registered completion date
March 2025
Finish at recent pace
December 2026
Construction started
September 2018
First registered
April 2018
Community
Tilal Al Ghaf
Units
35
Escrow bank
Emirates NBD
Name in Arabic
إليزيان مانشنس
Project number
2054
Site inspections
14

Schedule

Elysian Mansions was registered to complete in March 2025, 20 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%2019202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 August 2026

95%+2.0 pts

  • Elysian Mansions construction site, inspection photo 1, 14 August 2026
  • Elysian Mansions construction site, inspection photo 2, 14 August 2026
  • Elysian Mansions construction site, inspection photo 3, 14 August 2026
  • Elysian Mansions construction site, inspection photo 4, 14 August 2026

25 June 2026

93%+0.9 pts

  • Elysian Mansions construction site, inspection photo 1, 25 June 2026
  • Elysian Mansions construction site, inspection photo 2, 25 June 2026
  • Elysian Mansions construction site, inspection photo 3, 25 June 2026
  • Elysian Mansions construction site, inspection photo 4, 25 June 2026

4 June 2026

92%+1.0 pts

  • Elysian Mansions construction site, inspection photo 1, 4 June 2026
  • Elysian Mansions construction site, inspection photo 2, 4 June 2026
  • Elysian Mansions construction site, inspection photo 3, 4 June 2026
  • Elysian Mansions construction site, inspection photo 4, 4 June 2026

21 April 2026

91%+3.1 pts

  • Elysian Mansions construction site, inspection photo 1, 21 April 2026
  • Elysian Mansions construction site, inspection photo 2, 21 April 2026
  • Elysian Mansions construction site, inspection photo 3, 21 April 2026
  • Elysian Mansions construction site, inspection photo 4, 21 April 2026

21 January 2026

88%+8.5 pts

  • Elysian Mansions construction site, inspection photo 1, 21 January 2026
  • Elysian Mansions construction site, inspection photo 2, 21 January 2026
  • Elysian Mansions construction site, inspection photo 3, 21 January 2026
  • Elysian Mansions construction site, inspection photo 4, 21 January 2026

9 September 2025

80%+14 pts

  • Elysian Mansions construction site, inspection photo 1, 9 September 2025
  • Elysian Mansions construction site, inspection photo 2, 9 September 2025
  • Elysian Mansions construction site, inspection photo 3, 9 September 2025
  • Elysian Mansions construction site, inspection photo 4, 9 September 2025

16 June 2025

66%+20 pts

  • Elysian Mansions construction site, inspection photo 1, 16 June 2025
  • Elysian Mansions construction site, inspection photo 2, 16 June 2025
  • Elysian Mansions construction site, inspection photo 3, 16 June 2025
  • Elysian Mansions construction site, inspection photo 4, 16 June 2025

27 December 2024

46%+8.6 pts

  • Elysian Mansions construction site, inspection photo 1, 27 December 2024
  • Elysian Mansions construction site, inspection photo 2, 27 December 2024
  • Elysian Mansions construction site, inspection photo 3, 27 December 2024
  • Elysian Mansions construction site, inspection photo 4, 27 December 2024

31 October 2024

37%+22 pts

  • Elysian Mansions construction site, inspection photo 1, 31 October 2024
  • Elysian Mansions construction site, inspection photo 2, 31 October 2024
  • Elysian Mansions construction site, inspection photo 3, 31 October 2024
  • Elysian Mansions construction site, inspection photo 4, 31 October 2024

16 July 2024

16%+3.7 pts

  • Elysian Mansions construction site, inspection photo 1, 16 July 2024
  • Elysian Mansions construction site, inspection photo 2, 16 July 2024
  • Elysian Mansions construction site, inspection photo 3, 16 July 2024
  • Elysian Mansions construction site, inspection photo 4, 16 July 2024

All 100 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Elysian Mansions?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elysian Mansions handover date?
The registered completion date was March 2025, and the register still lists Elysian Mansions as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elysian Mansions?
Elysian Mansions was 95% built at the site inspection on 14 August 2026. The site has been inspected 14 times since February 2022. The Land Department took 100 site photos at its inspections.
Is Elysian Mansions delayed?
Yes. Its registered completion date of March 2025 has passed and the project is still listed as under construction.
Who is building Elysian Mansions?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Elysian Mansions?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.