Alaya construction progress

Alaya in Tilal Al Ghaf was registered to complete in July 2026 and is still under construction. At the last site inspection, in November 2026, it was 94% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

94%

Built, at the site inspection of 9 November 2026

4 months past its registered completion date

Registered completion date
July 2026
Finish at recent pace
February 2027
Construction started
March 2022
First registered
November 2021
Community
Tilal Al Ghaf
Units
46
Escrow bank
Emirates NBD
Name in Arabic
علايا
Project number
2322
Site inspections
16

Schedule

Alaya was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

94%+3.0 pts

  • Alaya construction site, inspection photo 1, 9 November 2026
  • Alaya construction site, inspection photo 2, 9 November 2026
  • Alaya construction site, inspection photo 3, 9 November 2026
  • Alaya construction site, inspection photo 4, 9 November 2026

14 August 2026

91%+3.4 pts

  • Alaya construction site, inspection photo 1, 14 August 2026
  • Alaya construction site, inspection photo 2, 14 August 2026
  • Alaya construction site, inspection photo 3, 14 August 2026
  • Alaya construction site, inspection photo 4, 14 August 2026

10 June 2026

88%+3.0 pts

  • Alaya construction site, inspection photo 1, 10 June 2026
  • Alaya construction site, inspection photo 2, 10 June 2026
  • Alaya construction site, inspection photo 3, 10 June 2026
  • Alaya construction site, inspection photo 4, 10 June 2026

17 March 2026

85%+5.9 pts

  • Alaya construction site, inspection photo 1, 17 March 2026
  • Alaya construction site, inspection photo 2, 17 March 2026
  • Alaya construction site, inspection photo 3, 17 March 2026
  • Alaya construction site, inspection photo 4, 17 March 2026

26 January 2026

79%+16 pts

  • Alaya construction site, inspection photo 1, 26 January 2026
  • Alaya construction site, inspection photo 2, 26 January 2026
  • Alaya construction site, inspection photo 3, 26 January 2026
  • Alaya construction site, inspection photo 4, 26 January 2026

21 October 2025

63%+2.1 pts

  • Alaya construction site, inspection photo 1, 21 October 2025
  • Alaya construction site, inspection photo 2, 21 October 2025
  • Alaya construction site, inspection photo 3, 21 October 2025
  • Alaya construction site, inspection photo 4, 21 October 2025

20 August 2025

61%+15 pts

  • Alaya construction site, inspection photo 1, 20 August 2025
  • Alaya construction site, inspection photo 2, 20 August 2025
  • Alaya construction site, inspection photo 3, 20 August 2025
  • Alaya construction site, inspection photo 4, 20 August 2025

1 May 2025

46%+9.6 pts

  • Alaya construction site, inspection photo 1, 1 May 2025
  • Alaya construction site, inspection photo 2, 1 May 2025
  • Alaya construction site, inspection photo 3, 1 May 2025
  • Alaya construction site, inspection photo 4, 1 May 2025

5 March 2025

37%+14 pts

  • Alaya construction site, inspection photo 1, 5 March 2025
  • Alaya construction site, inspection photo 2, 5 March 2025
  • Alaya construction site, inspection photo 3, 5 March 2025
  • Alaya construction site, inspection photo 4, 5 March 2025

15 November 2024

23%+15 pts

  • Alaya construction site, inspection photo 1, 15 November 2024
  • Alaya construction site, inspection photo 2, 15 November 2024
  • Alaya construction site, inspection photo 3, 15 November 2024
  • Alaya construction site, inspection photo 4, 15 November 2024

All 121 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Alaya?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Alaya handover date?
The registered completion date was July 2026, and the register still lists Alaya as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Alaya?
Alaya was 94% built at the site inspection on 9 November 2026. The site has been inspected 16 times since June 2022. The Land Department took 121 site photos at its inspections.
Is Alaya delayed?
Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
Who is building Alaya?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Alaya?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.