Alaya construction progress
Alaya in Tilal Al Ghaf was registered to complete in July 2026 and is still under construction. At the last site inspection, in November 2026, it was 94% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.
94%
Built, at the site inspection of 9 November 2026
4 months past its registered completion date
- Registered completion date
- July 2026
- Finish at recent pace
- February 2027
- Construction started
- March 2022
- First registered
- November 2021
- Community
- Tilal Al Ghaf
- Units
- 46
- Escrow bank
- Emirates NBD
- Name in Arabic
- علايا
- Project number
- 2322
- Site inspections
- 16
Schedule
Alaya was registered to complete in July 2026, 4 months ago, and is still under construction. Over the last year of inspections it has added about 1.6 points a month. Kept at that rate, the site would reach 100% around February 2027.
Site inspections
9 November 2026
94%+3.0 pts
14 August 2026
91%+3.4 pts
10 June 2026
88%+3.0 pts
17 March 2026
85%+5.9 pts
26 January 2026
79%+16 pts
21 October 2025
63%+2.1 pts
20 August 2025
61%+15 pts
1 May 2025
46%+9.6 pts
5 March 2025
37%+14 pts
15 November 2024
23%+15 pts
Context
Tilal Al Ghaf has 6 projects under construction, 73% built on average.
Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in Alaya?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Alaya handover date?
- The registered completion date was July 2026, and the register still lists Alaya as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Alaya?
- Alaya was 94% built at the site inspection on 9 November 2026. The site has been inspected 16 times since June 2022. The Land Department took 121 site photos at its inspections.
- Is Alaya delayed?
- Yes. Its registered completion date of July 2026 has passed and the project is still listed as under construction.
- Who is building Alaya?
- The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Alaya?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elysian MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 95%, Due March 2025, passed.
- Lanai IslandAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 61%, Due September 2026, passed.
- Serenity MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 40%.
- Plagette 32Also by Majid Al Futtaim Tilal Al Ghaf Phase A. 70%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)