Lanai Island construction progress

Lanai Island in Tilal Al Ghaf was registered to complete in September 2026 and is still under construction. At the last site inspection, in September 2026, it was 61% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

61%

Built, at the site inspection of 9 September 2026

2 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
October 2027
Construction started
April 2023
First registered
November 2022
Community
Tilal Al Ghaf
Units
27
Escrow bank
Emirates NBD
Name in Arabic
لاناي آيلاند
Project number
2498
Site inspections
11

Schedule

Lanai Island was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around October 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 September 2026

61%+2.1 pts

  • Lanai Island construction site, inspection photo 1, 9 September 2026
  • Lanai Island construction site, inspection photo 2, 9 September 2026
  • Lanai Island construction site, inspection photo 3, 9 September 2026
  • Lanai Island construction site, inspection photo 4, 9 September 2026

10 August 2026

59%+10 pts

  • Lanai Island construction site, inspection photo 1, 10 August 2026
  • Lanai Island construction site, inspection photo 2, 10 August 2026
  • Lanai Island construction site, inspection photo 3, 10 August 2026
  • Lanai Island construction site, inspection photo 4, 10 August 2026

2 April 2026

48%+2.4 pts

  • Lanai Island construction site, inspection photo 1, 2 April 2026
  • Lanai Island construction site, inspection photo 2, 2 April 2026
  • Lanai Island construction site, inspection photo 3, 2 April 2026
  • Lanai Island construction site, inspection photo 4, 2 April 2026

11 February 2026

46%+17 pts

  • Lanai Island construction site, inspection photo 1, 11 February 2026
  • Lanai Island construction site, inspection photo 2, 11 February 2026
  • Lanai Island construction site, inspection photo 3, 11 February 2026
  • Lanai Island construction site, inspection photo 4, 11 February 2026

20 October 2025

29%+9.2 pts

  • Lanai Island construction site, inspection photo 1, 20 October 2025
  • Lanai Island construction site, inspection photo 2, 20 October 2025
  • Lanai Island construction site, inspection photo 3, 20 October 2025
  • Lanai Island construction site, inspection photo 4, 20 October 2025

17 July 2025

19%+5.8 pts

  • Lanai Island construction site, inspection photo 1, 17 July 2025
  • Lanai Island construction site, inspection photo 2, 17 July 2025
  • Lanai Island construction site, inspection photo 3, 17 July 2025
  • Lanai Island construction site, inspection photo 4, 17 July 2025

20 January 2025

14%+8.5 pts

  • Lanai Island construction site, inspection photo 1, 20 January 2025
  • Lanai Island construction site, inspection photo 2, 20 January 2025
  • Lanai Island construction site, inspection photo 3, 20 January 2025
  • Lanai Island construction site, inspection photo 4, 20 January 2025

18 December 2024

5.1%+4.6 pts

  • Lanai Island construction site, inspection photo 1, 18 December 2024
  • Lanai Island construction site, inspection photo 2, 18 December 2024
  • Lanai Island construction site, inspection photo 3, 18 December 2024
  • Lanai Island construction site, inspection photo 4, 18 December 2024

1 May 2024

0.6%+0.4 pts

  • Lanai Island construction site, inspection photo 1, 1 May 2024
  • Lanai Island construction site, inspection photo 2, 1 May 2024

17 July 2023

0.1%+0.0 pts

  • Lanai Island construction site, inspection photo 1, 17 July 2023
  • Lanai Island construction site, inspection photo 2, 17 July 2023
  • Lanai Island construction site, inspection photo 3, 17 July 2023

All 70 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Lanai Island?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lanai Island handover date?
The registered completion date was September 2026, and the register still lists Lanai Island as under construction. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lanai Island?
Lanai Island was 61% built at the site inspection on 9 September 2026. The site has been inspected 11 times since November 2022. The Land Department took 70 site photos at its inspections.
Is Lanai Island delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Lanai Island?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Lanai Island?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.