Lanai Island construction progress

Lanai Island in Tilal Al Ghaf is 61% built at the Land Department inspection of September 2026. Developer Majid Al Futtaim Tilal Al Ghaf Phase A. Completion registered for September 2026.

61%

Built, at the Land Department site inspection of 9 September 2026

0 months past its registered completion date

Completion date (Land Department)
September 2026
Finish at recent pace
October 2027
Construction started
April 2023
Registered with the Land Department
November 2022
Community
Tilal Al Ghaf
Units
27
Escrow bank
Emirates NBD
Name in Arabic
لاناي آيلاند
Land Department project number
2498
Land Department site inspections
11

Schedule

Lanai Island was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around October 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 September 2026

61%+2.1 pts

  • Lanai Island construction site, Land Department inspection photo 1, 9 September 2026
  • Lanai Island construction site, Land Department inspection photo 2, 9 September 2026
  • Lanai Island construction site, Land Department inspection photo 3, 9 September 2026
  • Lanai Island construction site, Land Department inspection photo 4, 9 September 2026

10 August 2026

59%+10 pts

  • Lanai Island construction site, Land Department inspection photo 1, 10 August 2026
  • Lanai Island construction site, Land Department inspection photo 2, 10 August 2026
  • Lanai Island construction site, Land Department inspection photo 3, 10 August 2026
  • Lanai Island construction site, Land Department inspection photo 4, 10 August 2026

2 April 2026

48%+2.4 pts

  • Lanai Island construction site, Land Department inspection photo 1, 2 April 2026
  • Lanai Island construction site, Land Department inspection photo 2, 2 April 2026
  • Lanai Island construction site, Land Department inspection photo 3, 2 April 2026
  • Lanai Island construction site, Land Department inspection photo 4, 2 April 2026

11 February 2026

46%+17 pts

  • Lanai Island construction site, Land Department inspection photo 1, 11 February 2026
  • Lanai Island construction site, Land Department inspection photo 2, 11 February 2026
  • Lanai Island construction site, Land Department inspection photo 3, 11 February 2026
  • Lanai Island construction site, Land Department inspection photo 4, 11 February 2026

20 October 2025

29%+9.2 pts

  • Lanai Island construction site, Land Department inspection photo 1, 20 October 2025
  • Lanai Island construction site, Land Department inspection photo 2, 20 October 2025
  • Lanai Island construction site, Land Department inspection photo 3, 20 October 2025
  • Lanai Island construction site, Land Department inspection photo 4, 20 October 2025

17 July 2025

19%+5.8 pts

  • Lanai Island construction site, Land Department inspection photo 1, 17 July 2025
  • Lanai Island construction site, Land Department inspection photo 2, 17 July 2025
  • Lanai Island construction site, Land Department inspection photo 3, 17 July 2025
  • Lanai Island construction site, Land Department inspection photo 4, 17 July 2025

20 January 2025

14%+8.5 pts

  • Lanai Island construction site, Land Department inspection photo 1, 20 January 2025
  • Lanai Island construction site, Land Department inspection photo 2, 20 January 2025
  • Lanai Island construction site, Land Department inspection photo 3, 20 January 2025
  • Lanai Island construction site, Land Department inspection photo 4, 20 January 2025

18 December 2024

5.1%+4.6 pts

  • Lanai Island construction site, Land Department inspection photo 1, 18 December 2024
  • Lanai Island construction site, Land Department inspection photo 2, 18 December 2024
  • Lanai Island construction site, Land Department inspection photo 3, 18 December 2024
  • Lanai Island construction site, Land Department inspection photo 4, 18 December 2024

1 May 2024

0.6%+0.4 pts

  • Lanai Island construction site, Land Department inspection photo 1, 1 May 2024
  • Lanai Island construction site, Land Department inspection photo 2, 1 May 2024

17 July 2023

0.1%+0.0 pts

  • Lanai Island construction site, Land Department inspection photo 1, 17 July 2023
  • Lanai Island construction site, Land Department inspection photo 2, 17 July 2023
  • Lanai Island construction site, Land Department inspection photo 3, 17 July 2023

All 70 site photos, by inspection date

Context

Tilal Al Ghaf has 5 projects under construction, 64% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Lanai Island?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lanai Island be completed?
The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Lanai Island is built?
61%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 11 times since November 2022.
Is Lanai Island delayed?
Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
Who is building Lanai Island?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Lanai Island?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.