Lanai Island construction progress
Lanai Island in Tilal Al Ghaf is 61% built at the Land Department inspection of September 2026. Developer Majid Al Futtaim Tilal Al Ghaf Phase A. Completion registered for September 2026.
61%
Built, at the Land Department site inspection of 9 September 2026
0 months past its registered completion date
- Completion date (Land Department)
- September 2026
- Finish at recent pace
- October 2027
- Construction started
- April 2023
- Registered with the Land Department
- November 2022
- Community
- Tilal Al Ghaf
- Units
- 27
- Escrow bank
- Emirates NBD
- Name in Arabic
- لاناي آيلاند
- Land Department project number
- 2498
- Land Department site inspections
- 11
Schedule
Lanai Island was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around October 2027.
Site inspections
9 September 2026
61%+2.1 pts
10 August 2026
59%+10 pts
2 April 2026
48%+2.4 pts
11 February 2026
46%+17 pts
20 October 2025
29%+9.2 pts
17 July 2025
19%+5.8 pts
20 January 2025
14%+8.5 pts
18 December 2024
5.1%+4.6 pts
1 May 2024
0.6%+0.4 pts
17 July 2023
0.1%+0.0 pts
Context
Tilal Al Ghaf has 5 projects under construction, 64% built on average.
Majid Al Futtaim Tilal Al Ghaf Phase A has 5 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Lanai Island?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Lanai Island be completed?
- The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Lanai Island is built?
- 61%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 11 times since November 2022.
- Is Lanai Island delayed?
- Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
- Who is building Lanai Island?
- The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Lanai Island?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Elysian MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 95%, Due March 2025, passed.
- Serenity MansionsAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 32%.
- Plagette 32Also by Majid Al Futtaim Tilal Al Ghaf Phase A. 61%.
- AmaraAlso by Majid Al Futtaim Tilal Al Ghaf Phase A. 71%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.