Lanai Island construction photos
70 photos taken by Dubai Land Department engineers at 11 site inspections, newest first. The percentage is how much of Lanai Island was built on the day of each visit.
9 September 202661% built
10 August 202659% built
2 April 202648% built
11 February 202646% built
20 October 202529% built
17 July 202519% built
20 January 202514% built
18 December 20245.1% built
1 May 20240.6% built
17 July 20230.1% built
3 November 20220.1% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.















.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)