Elan construction progress

The register lists Elan in Tilal Al Ghaf as complete, with a registered completion date of November 2023. Its last site inspection on record was in November 2023. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

100%

Built, at the site inspection of 3 November 2023

Construction complete

Registered completion date
November 2023
Construction started
June 2020
First registered
February 2020
Community
Tilal Al Ghaf
Units
916
Escrow bank
Emirates NBD
Name in Arabic
إيلان
Project number
2205
Site inspections
10

Schedule

The register lists Elan as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2023

100%+2.0 pts

  • Elan construction site, inspection photo 1, 3 November 2023
  • Elan construction site, inspection photo 2, 3 November 2023
  • Elan construction site, inspection photo 3, 3 November 2023
  • Elan construction site, inspection photo 4, 3 November 2023

17 July 2023

98%+16 pts

  • Elan construction site, inspection photo 1, 17 July 2023
  • Elan construction site, inspection photo 2, 17 July 2023
  • Elan construction site, inspection photo 3, 17 July 2023
  • Elan construction site, inspection photo 4, 17 July 2023

23 March 2023

82%+12 pts

  • Elan construction site, inspection photo 1, 23 March 2023
  • Elan construction site, inspection photo 2, 23 March 2023
  • Elan construction site, inspection photo 3, 23 March 2023
  • Elan construction site, inspection photo 4, 23 March 2023

23 November 2022

70%+12 pts

  • Elan construction site, inspection photo 1, 23 November 2022
  • Elan construction site, inspection photo 2, 23 November 2022
  • Elan construction site, inspection photo 3, 23 November 2022
  • Elan construction site, inspection photo 4, 23 November 2022

28 July 2022

58%+15 pts

  • Elan construction site, inspection photo 1, 28 July 2022
  • Elan construction site, inspection photo 2, 28 July 2022
  • Elan construction site, inspection photo 3, 28 July 2022
  • Elan construction site, inspection photo 4, 28 July 2022

10 March 2022

42%+15 pts

  • Elan construction site, inspection photo 1, 10 March 2022
  • Elan construction site, inspection photo 2, 10 March 2022
  • Elan construction site, inspection photo 3, 10 March 2022
  • Elan construction site, inspection photo 4, 10 March 2022

8 November 2021

27%+18 pts

  • Elan construction site, inspection photo 1, 8 November 2021
  • Elan construction site, inspection photo 2, 8 November 2021
  • Elan construction site, inspection photo 3, 8 November 2021
  • Elan construction site, inspection photo 4, 8 November 2021

7 July 2021

8.9%+5.9 pts

  • Elan construction site, inspection photo 1, 7 July 2021
  • Elan construction site, inspection photo 2, 7 July 2021
  • Elan construction site, inspection photo 3, 7 July 2021
  • Elan construction site, inspection photo 4, 7 July 2021

24 February 2021

3.0%+2.3 pts

  • Elan construction site, inspection photo 1, 24 February 2021
  • Elan construction site, inspection photo 2, 24 February 2021
  • Elan construction site, inspection photo 3, 24 February 2021
  • Elan construction site, inspection photo 4, 24 February 2021

16 August 2020

0.7%

  • Elan construction site, inspection photo 1, 16 August 2020
  • Elan construction site, inspection photo 2, 16 August 2020
  • Elan construction site, inspection photo 3, 16 August 2020
  • Elan construction site, inspection photo 4, 16 August 2020

All 100 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Elan?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Elan handover date?
Construction of Elan is recorded as complete, with a registered completion date of November 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Elan?
Elan was 100% built at the site inspection on 3 November 2023. The site has been inspected 10 times since August 2020. The Land Department took 100 site photos at its inspections.
Is Elan delayed?
The register lists construction as complete.
Who is building Elan?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Elan?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.