Elan construction photos

100 photos from 10 site inspections, newest first. The percentage is how much of Elan was built on the day of each visit.

3 November 2023100% built

17 July 202398% built

23 March 202382% built

23 November 202270% built

28 July 202258% built

10 March 202242% built

8 November 202127% built

7 July 20218.9% built

24 February 20213.0% built

16 August 20200.7% built

Back to Elan construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.