Amara construction progress

No completion date is registered for Amara in Tilal Al Ghaf yet. At the last site inspection, in November 2026, it was 77% built. The developer is Majid Al Futtaim Tilal Al Ghaf Phase A.

77%

Built, at the site inspection of 17 November 2026

Finish at recent pace
March 2027
Construction started
June 2024
First registered
December 2023
Community
Tilal Al Ghaf
Units
116
Escrow bank
Emirates NBD
Name in Arabic
أمارا
Project number
2858
Site inspections
9

Schedule

Since January 2026 Amara has added about 5.2 points a month. At that rate the site reaches 100% around March 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

17 November 2026

77%+6.5 pts

  • Amara construction site, inspection photo 1, 17 November 2026
  • Amara construction site, inspection photo 2, 17 November 2026
  • Amara construction site, inspection photo 3, 17 November 2026
  • Amara construction site, inspection photo 4, 17 November 2026

13 August 2026

71%+13 pts

  • Amara construction site, inspection photo 1, 13 August 2026
  • Amara construction site, inspection photo 2, 13 August 2026
  • Amara construction site, inspection photo 3, 13 August 2026
  • Amara construction site, inspection photo 4, 13 August 2026

8 July 2026

58%+17 pts

  • Amara construction site, inspection photo 1, 8 July 2026
  • Amara construction site, inspection photo 2, 8 July 2026
  • Amara construction site, inspection photo 3, 8 July 2026
  • Amara construction site, inspection photo 4, 8 July 2026

16 April 2026

41%+15 pts

  • Amara construction site, inspection photo 1, 16 April 2026
  • Amara construction site, inspection photo 2, 16 April 2026
  • Amara construction site, inspection photo 3, 16 April 2026
  • Amara construction site, inspection photo 4, 16 April 2026

13 January 2026

25%+19 pts

  • Amara construction site, inspection photo 1, 13 January 2026
  • Amara construction site, inspection photo 2, 13 January 2026
  • Amara construction site, inspection photo 3, 13 January 2026
  • Amara construction site, inspection photo 4, 13 January 2026

6 October 2025

6.6%+2.3 pts

  • Amara construction site, inspection photo 1, 6 October 2025
  • Amara construction site, inspection photo 2, 6 October 2025
  • Amara construction site, inspection photo 3, 6 October 2025
  • Amara construction site, inspection photo 4, 6 October 2025

18 August 2025

4.3%+3.7 pts

  • Amara construction site, inspection photo 1, 18 August 2025
  • Amara construction site, inspection photo 2, 18 August 2025
  • Amara construction site, inspection photo 3, 18 August 2025
  • Amara construction site, inspection photo 4, 18 August 2025

24 January 2025

0.6%+0.6 pts

  • Amara construction site, inspection photo 1, 24 January 2025
  • Amara construction site, inspection photo 2, 24 January 2025
  • Amara construction site, inspection photo 3, 24 January 2025

27 November 2023

0%

  • Amara construction site, inspection photo 1, 27 November 2023
  • Amara construction site, inspection photo 2, 27 November 2023

All 74 site photos, by inspection date

Context

Tilal Al Ghaf has 6 projects under construction, 73% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 6 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Amara?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Amara handover date?
No completion date is on record for Amara yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Amara?
Amara was 77% built at the site inspection on 17 November 2026. The site has been inspected 9 times since November 2023. The Land Department took 74 site photos at its inspections.
Who is building Amara?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Amara?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.