Amara construction progress

Amara in Tilal Al Ghaf is 71% built at the Land Department inspection of August 2026. Developer Majid Al Futtaim Tilal Al Ghaf Phase A.

71%

Built, at the Land Department site inspection of 13 August 2026

Finish at recent pace
January 2027
Construction started
June 2024
Registered with the Land Department
December 2023
Community
Tilal Al Ghaf
Units
116
Escrow bank
Emirates NBD
Name in Arabic
أمارا
Land Department project number
2858
Land Department site inspections
8

Schedule

Since August 2025 Amara has added about 5.6 points a month. At that rate the site reaches 100% around January 2027. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

13 August 2026

71%+13 pts

  • Amara construction site, Land Department inspection photo 1, 13 August 2026
  • Amara construction site, Land Department inspection photo 2, 13 August 2026
  • Amara construction site, Land Department inspection photo 3, 13 August 2026
  • Amara construction site, Land Department inspection photo 4, 13 August 2026

8 July 2026

58%+17 pts

  • Amara construction site, Land Department inspection photo 1, 8 July 2026
  • Amara construction site, Land Department inspection photo 2, 8 July 2026
  • Amara construction site, Land Department inspection photo 3, 8 July 2026
  • Amara construction site, Land Department inspection photo 4, 8 July 2026

16 April 2026

41%+15 pts

  • Amara construction site, Land Department inspection photo 1, 16 April 2026
  • Amara construction site, Land Department inspection photo 2, 16 April 2026
  • Amara construction site, Land Department inspection photo 3, 16 April 2026
  • Amara construction site, Land Department inspection photo 4, 16 April 2026

13 January 2026

25%+19 pts

  • Amara construction site, Land Department inspection photo 1, 13 January 2026
  • Amara construction site, Land Department inspection photo 2, 13 January 2026
  • Amara construction site, Land Department inspection photo 3, 13 January 2026
  • Amara construction site, Land Department inspection photo 4, 13 January 2026

6 October 2025

6.6%+2.3 pts

  • Amara construction site, Land Department inspection photo 1, 6 October 2025
  • Amara construction site, Land Department inspection photo 2, 6 October 2025
  • Amara construction site, Land Department inspection photo 3, 6 October 2025
  • Amara construction site, Land Department inspection photo 4, 6 October 2025

18 August 2025

4.3%+3.7 pts

  • Amara construction site, Land Department inspection photo 1, 18 August 2025
  • Amara construction site, Land Department inspection photo 2, 18 August 2025
  • Amara construction site, Land Department inspection photo 3, 18 August 2025
  • Amara construction site, Land Department inspection photo 4, 18 August 2025

24 January 2025

0.6%+0.6 pts

  • Amara construction site, Land Department inspection photo 1, 24 January 2025
  • Amara construction site, Land Department inspection photo 2, 24 January 2025
  • Amara construction site, Land Department inspection photo 3, 24 January 2025

27 November 2023

0%

  • Amara construction site, Land Department inspection photo 1, 27 November 2023
  • Amara construction site, Land Department inspection photo 2, 27 November 2023

All 61 site photos, by inspection date

Context

Tilal Al Ghaf has 5 projects under construction, 64% built on average.

Majid Al Futtaim Tilal Al Ghaf Phase A has 5 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Amara?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Amara be completed?
The Land Department has no completion date on record for Amara yet.
How much of Amara is built?
71%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 8 times since November 2023.
Who is building Amara?
The registered developer is Majid Al Futtaim Tilal Al Ghaf Phase A. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Amara?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.