Amara construction photos

61 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Amara was built on the day of each visit.

13 August 202671% built

8 July 202658% built

16 April 202641% built

13 January 202625% built

6 October 20256.6% built

18 August 20254.3% built

24 January 20250.6% built

27 November 20230% built

Back to Amara construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.