121 photos from 16 site inspections, newest first. The percentage is how much of Alaya was built on the day of each visit.

9 November 202694% built

14 August 202691% built

10 June 202688% built

17 March 202685% built

26 January 202679% built

21 October 202563% built

20 August 202561% built

1 May 202546% built

5 March 202537% built

15 November 202423% built

24 July 20248.1% built

1 May 20242.3% built

17 July 20230.8% built

7 March 20230.7% built

1 November 20220.5% built

7 June 20220.3% built

Back to Alaya construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.