The Heart Of Europe 1 construction progress

The Heart Of Europe 1 in The World was registered to complete in September 2022 and is still under construction. At the last site inspection, in May 2026, it was 86% built. The developer is T H O E Real Estate Development.

86%

Built, at the site inspection of 12 May 2026

50 months past its registered completion date

Registered completion date
September 2022
Finish at recent pace
April 2033
Construction started
January 2016
First registered
December 2016
Community
The World
Units
32
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا هارت اوف يوروب 1
Project number
1777
Site inspections
16

Schedule

The Heart Of Europe 1 was registered to complete in September 2022, 50 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around April 2033.

0%25%50%75%100%20172019202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 May 2026

86%+1.7 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 12 May 2026
  • The Heart Of Europe 1 construction site, inspection photo 2, 12 May 2026
  • The Heart Of Europe 1 construction site, inspection photo 3, 12 May 2026
  • The Heart Of Europe 1 construction site, inspection photo 4, 12 May 2026

29 June 2025

84%+6.4 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 29 June 2025
  • The Heart Of Europe 1 construction site, inspection photo 2, 29 June 2025
  • The Heart Of Europe 1 construction site, inspection photo 3, 29 June 2025
  • The Heart Of Europe 1 construction site, inspection photo 4, 29 June 2025

4 July 2022

78%+0.1 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 4 July 2022
  • The Heart Of Europe 1 construction site, inspection photo 2, 4 July 2022
  • The Heart Of Europe 1 construction site, inspection photo 3, 4 July 2022
  • The Heart Of Europe 1 construction site, inspection photo 4, 4 July 2022

10 January 2022

78%+0.3 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 10 January 2022
  • The Heart Of Europe 1 construction site, inspection photo 2, 10 January 2022
  • The Heart Of Europe 1 construction site, inspection photo 3, 10 January 2022
  • The Heart Of Europe 1 construction site, inspection photo 4, 10 January 2022

11 August 2021

78%+5.0 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 11 August 2021
  • The Heart Of Europe 1 construction site, inspection photo 2, 11 August 2021
  • The Heart Of Europe 1 construction site, inspection photo 3, 11 August 2021
  • The Heart Of Europe 1 construction site, inspection photo 4, 11 August 2021

17 March 2021

73%+0.7 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 17 March 2021
  • The Heart Of Europe 1 construction site, inspection photo 2, 17 March 2021
  • The Heart Of Europe 1 construction site, inspection photo 3, 17 March 2021
  • The Heart Of Europe 1 construction site, inspection photo 4, 17 March 2021

9 March 2020

72%+5.8 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 9 March 2020
  • The Heart Of Europe 1 construction site, inspection photo 2, 9 March 2020
  • The Heart Of Europe 1 construction site, inspection photo 3, 9 March 2020
  • The Heart Of Europe 1 construction site, inspection photo 4, 9 March 2020

27 August 2019

66%+5.9 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 27 August 2019
  • The Heart Of Europe 1 construction site, inspection photo 2, 27 August 2019
  • The Heart Of Europe 1 construction site, inspection photo 3, 27 August 2019
  • The Heart Of Europe 1 construction site, inspection photo 4, 27 August 2019

21 May 2019

60%+8.0 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 21 May 2019
  • The Heart Of Europe 1 construction site, inspection photo 2, 21 May 2019
  • The Heart Of Europe 1 construction site, inspection photo 3, 21 May 2019
  • The Heart Of Europe 1 construction site, inspection photo 4, 21 May 2019

24 February 2019

52%+7.2 pts

  • The Heart Of Europe 1 construction site, inspection photo 1, 24 February 2019
  • The Heart Of Europe 1 construction site, inspection photo 2, 24 February 2019
  • The Heart Of Europe 1 construction site, inspection photo 3, 24 February 2019
  • The Heart Of Europe 1 construction site, inspection photo 4, 24 February 2019

All 171 site photos, by inspection date

Context

The World has 7 projects under construction, 66% built on average.

T H O E Real Estate Development has 4 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in The Heart Of Europe 1?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Heart Of Europe 1 handover date?
The registered completion date was September 2022, and the register still lists The Heart Of Europe 1 as under construction. At the pace of its recent inspections the site would reach 100% around April 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Heart Of Europe 1?
The Heart Of Europe 1 was 86% built at the site inspection on 12 May 2026. The site has been inspected 16 times since August 2017. The Land Department took 171 site photos at its inspections.
Is The Heart Of Europe 1 delayed?
Yes. Its registered completion date of September 2022 has passed and the project is still listed as under construction.
Who is building The Heart Of Europe 1?
The registered developer is T H O E Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Heart Of Europe 1?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.